Inspection Status: Passed
Inspection History: COT - LCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 02/19/2025 |
COT - LCPL - Plumbing Progress |
|
Passed |
2/19/25: Domestic water supply lines are complete and under 150 psi air test with no leaks. |
| 06/07/2024 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
6/7/24: treatment cell 2nd floor drains under test will install before pour with wrap. |
| 07/08/2024 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
7/8/24: Chill water lines are under 150 pound air pressure test with no leaks. Okay to proceed with wrapping pipes before concrete pour. |
| 07/12/2024 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
7/12/24: 200' of 2" pipe and 300' of 1" chill water lines are under 150 pound air pressure test with no leaks. Pipe fitters are wrapping pipes before concrete pour. |
| 10/16/2024 |
COT - LCPL - Plumbing Progress |
|
Partial Pass |
10/16/2024 From the PRV station 1 1/4” copper to back flow preventer, hose bib and wall hydrant. 1 1/4” tees off to IDF room. 3” main from PRV station water supply tees to 3/4 wall hydrant. Tees off too roof hydrant. 3” continues to dock office. Dock office 100% under test. 3” reduces to 2 1/2” after dock office to office main supply cold water line. Then tees off to 3/4 roof hydrant. Reduces to 2” to 2x1x2” tee capped 20’ stick capped west of main office. 1” supplies to 2 roof hydrants north of mezzanine. |