Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 04/18/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
4/18/24: partial for electrical conduit at treatment cell partition wall and west wall level one. |
| 05/03/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
5/3/24: level one east wall treatment cell electrical okay to cover |
| 07/02/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
X2 3/4” conduit schedule 80. Feeding smoke detectors at both east and west end of treatment cell. |
| 08/15/2024 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
8/15/24: needed electrical progress in mezzanine for pre concrete pour |
| 09/06/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
9/5/24: 9/5/24: mezzanine rotor room west and north walls okay to place concrete. Office areas and bathrooms okay to cover |
| 10/02/2024 |
COT - HCEL - Electrical Intermediate |
|
Passed |
10/2/24: Conduit and boxes are in place for fire alarm in mezzanine floor. Okay to pour concrete. |