Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Re-inspection required

Inspection History: COT - HCBU - Framing

Permit Number - TC-COM-0425-00796

Inspection Description - COT - HCBU - Framing

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
08/26/2025 COT - HCBU - Framing Re-inspection required 8-26-25: called contractor at 932am and received no answer. Contractor nor plans wfor Building 2 not on site and I don't have access to them on my tablet. Left site after waiting 10 minutes. Reschedule inspections when ready.
08/27/2025 COT - HCBU - Framing Re-inspection required 8-27-25: Building 2 metal stud wall framing inspection-Add power driven pins on track at 12" o.c. , missing header & studs, missing clip angles at each stud. See S-001 details 1, 2 & 6
09/03/2025 COT - HCBU - Framing Partial Pass 9-3-25: partial pass-Simpson MSUBH3.25's were used rather than clip angles at each stud-contractor will be submitting an RFI reflecting change. Okay to one side warehouse side at own risk pending RFI approval. Header to be inspected at later date.
09/12/2025 COT - HCBU - Framing Partial Pass 9/12/25: Drywall fastener per schedule at exterior side of south and east walls of office area. Partial pass for bathrooms framing in office area. Pending framing at warehouse restrooms.
11/10/2025 COT - HCBU - Framing Passed 11-10-25: approved.