Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Exterior Clips/Sheathing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | West elevation cripple stud walls. Sheathing in place. Approved. Screw inspection at plywood lower roof Approved. Okay to proceed progress areas. 5/29/2026 |
|
| 06/05/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 6-5-26: 12th floor infill framing/sheathing inspection for a total of 12 infill columns. Framing verified per A9.2/Detail 7-Pending infill tie-ins using nails/hilti screws. | |
| 06/09/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 6-9-26: 11th.floor framing/sheathing inspection on a total of 12 infill columns. Framing verified per A9.2/Detail 7-Pending infill tie-ins using nails/hilti screws. | |
| 06/12/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 6/12/2026 Partial pass. Level 10 Exterior framed wall and sheathing total of 12 infill columns approved. | |
| 06/25/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | ||
| 07/10/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 7/10/2026 Partial pass. Penthouse roof sheathing at parapet approved along with lower deck penthouse parapet walls. | |
| 07/22/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | ||
| 08/07/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 8-7-26: drywall screw inspection Level 11 exterior columns. Add screws to 2- exterior columns located at south west side. Remaining 10 exterior. Columns are okay to tape/texture. | |
| 10/06/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 10/6/26: inspected angle clips on each exterior columns on levels 4-8 with a total of 12 columns per floor. | |
| 10/09/2026 | COT - HCBU - Exterior Clips/Sheathing | Re-inspection required | ||
| 10/12/2026 | COT - HCBU - Exterior Clips/Sheathing | Partial Pass | 10/12/26: 2nd floor southeast RFI-4 verified L-Clips/ metal plate & screws at bottom of framing together with screws at 2nd floor southwest dens glass sheathing. Okay to continue with construction at progress areas. |