Inspection History Details
Inspection Status: Requested
Inspection History: COT - LCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - LCBU - Framing | Requested | |||
| 05/08/2026 | COT - LCBU - Framing | Partial Pass | 5-8-26: upper and lower roof at 3rd floor metal furr out channels (minus Northeast Corner of 3rd floor) and wood blocking/ parapet nailer for parapet cap properly secured. Okay to continue with construction at progress areas but reschedule northeast section of 3rd floor prior to covering. | |
| 05/12/2026 | COT - LCBU - Framing | Partial Pass | 5/12/26: lower roof at 3rd floor metal furr out channels Northeast Corner of 3rd floor. Okay to continue with construction at progress areas. | |
| 05/21/2026 | COT - LCBU - Framing | Partial Pass | 5/21/2026 3rd floor in fill at metal panel columns . Total of 12. Okay for water proofing. | |
| 05/29/2026 | COT - LCBU - Framing | Partial Pass | West elevation cripple stud walls. Sheathing in place. Approved. Screw inspection at plywood lower roof Approved. Okay to proceed progress areas. 5/29/2026 |
|
| 06/03/2026 | COT - LCBU - Framing | Partial Pass | North, east, & south west corner elevations cripple stud walls along with sheathing in place approved. Okay to proceed progress areas. 6/3/2026 | |
| 06/05/2026 | COT - LCBU - Framing | Partial Pass | 6-5-26: 12th floor infill framing/sheathing inspection for a total of 12 infill columns. Framing verified per A9.2/Detail 7-Pending infill tie-ins using nails/hilti screws. |