Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Building Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/26/2025 | COT - HCBU - Building Progress | Re-inspection required | 9-26-25: add shot pins 12" o.c. at sill and shot pins at top track-see schedule for details. | |
| 10/07/2025 | COT - HCBU - Building Progress | Partial Pass | Sheetrock nailing on West walls. Ok to tape progress areas. | |
| 10/10/2025 | COT - HCBU - Building Progress | Partial Pass | 10-10-25: pre-con meeting to discuss upcoming interior framing & MEP's requirements. | |
| 10/20/2025 | COT - HCBU - Building Progress | Partial Pass | 10-20-25: interior metal framing for Suite 190 approved. Okay to continue with construction at progress areas. | |
| 10/22/2025 | COT - HCBU - Building Progress | Partial Pass | 10-22-25: verified 2 demising walls for suite190. Okay to drywall progress areas. | |
| 10/23/2025 | COT - HCBU - Building Progress | Not Ready | 10-23-25: not entirely ready. Missing screws at several areas. Install drywall screws 3/8" from joints and per ASTM-screws cannot over penetrate more than 1/32". Bathrooms missing screws at base-will check at rein-spection. | |
| 10/24/2025 | COT - HCBU - Building Progress | Canceled | 10-24-25: canceled by contractor. | |
| 10/27/2025 | COT - HCBU - Building Progress | Partial Pass | 10-27-25: okay for tape & texture. | |
| 11/18/2025 | COT - HCBU - Building Progress | Partial Pass | 11-18-25: add stainless steel or galvanized screws for drywall at wet locations in bathrooms. | |
| 11/19/2025 | COT - HCBU - Building Progress | Not Ready | ||
| 11/20/2025 | COT - HCBU - Building Progress | Re-inspection required | 11-20-25: not ready. | |
| 11/21/2025 | COT - HCBU - Building Progress | Not Ready | 11-21-25: demising wall kickers at suite 190 were moved 4' o.c. To 20' o.c... Architect will be submitting an RFI showing change. Once RFI is in the system and under review you may proceed with installing the remaining drywall at own risk. Okay to tape & texture progress areas of demising wall. | |
| 11/25/2025 | COT - HCBU - Building Progress | Partial Pass | 11/25/2025 partial pass. Frame/Screw Inspection at new vestibule area approved. | |
| 12/01/2025 | COT - HCBU - Building Progress | Partial Pass | 12-1-25: RFI showing demising wall bracing at 20' o.c. has been submitted to the city for review. Okay to drywall upper section to bottom of decking at own risk. Schedule a screw inspection prior to tape & texture. | |
| 12/03/2025 | COT - HCBU - Building Progress | Partial Pass | 12.3.25 Partial pass for progress areas at top sheet rock fastener areas. Progress at far,I'm also inspected and approved to proceed. |
|
| 12/09/2025 | COT - HCBU - Building Progress | Canceled | 12-9-25: canceled by contractor. | |
| 12/30/2025 | COT - HCBU - Building Progress | Passed | 12-30-25: Suite's 190 & 150 vestibules are okay to tape & texture. Suite 150-vestibule electrical approved. |