Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
03/18/2025
Applicant:
Avinash Karnati
Description:
REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.

Permit Reviews

Permit Number - TC-COM-0325-00544
Permit Status: Complete
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.
Start Date Submittal Complete Date Status  
01/14/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/26/2026 APPROVED Review Details
05/20/2025 COMMERCIAL REVIEW - FULL v.3 05/20/2025 APPROVED Review Details
04/23/2025 COMMERCIAL REVIEW - FULL v.2 05/13/2025 REQUIRES RESUBMIT Review Details
05/20/2025 RESTAMP - COMMERCIAL v.1 05/28/2025 APPROVED Review Details
03/20/2025 COMMERCIAL REVIEW - FULL v.1 04/16/2025 REQUIRES RESUBMIT Review Details
10/29/2025 COMMERCIAL REVIEW - FULL REVISION v.1 11/18/2025 APPROVED Review Details
12/01/2025 COMMERCIAL REVIEW - FULL REVISION v.1 12/23/2025 APPROVED Review Details
09/02/2025 COMMERCIAL REVIEW - FULL REVISION v.1 09/29/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0325-00544
Permit Status: Complete
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.
Date Description Comments
03/20/2025 UNIT IDENTIFICATION
03/20/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
03/20/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
05/20/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
05/20/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0325-00544
Permite Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.
Total Outstanding Inspections - 11
Last Inspection Date Description Inspector Results Comments
09/15/2025 COT - HCPL - Plumbing Progress N/A Re-inspection required 9-15-25: arrived on site at approximately 950am and noted that pour back had already occurred. Therefore, provide a letter to the city for review & approval documenting that pour back at plumbing areas was done per the 2018 IBC and per approved plans. The Letter must be submitted & approved prior to releasing a C of O.
12/03/2025 COT - HCBU - Building Progress N/A Partial Pass 12.3.25
Partial pass for progress areas at top sheet rock fastener areas.
Progress at far,I'm also inspected and approved to proceed.
12/23/2025 COT - HCEL - Electrical Progress N/A Partial Pass 12-23-25: partial pass rough electrical at vestibule.
11/20/2025 COT - HCME - Mechanical Intermediate N/A Partial Pass 11-20-25: okay to install ceiling tiles.
10/10/2025 COT - HCME - Mechanical Progress N/A Canceled 10-10-25: canceled by contractor.
01/14/2026 COT - FCON - Alarm - Final N/A Not Applicable
01/05/2026 COT - HCBU - Building Final N/A Partial Pass 1-5-26: pre con meeting.
01/05/2026 COT - HCEL - Electrical Final N/A Canceled 1-5-26: canceled by contractor.
01/05/2026 COT - HCME - Mechanical Final N/A Canceled 1-5-26: canceled by contractor.
01/05/2026 COT - HCPL - Plumbing Final N/A Canceled 1-5-26: canceled by contractor.
01/21/2026 COT - BULD - SWG Clearance N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0325-00544
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.
Total Completed Inspections - 17
Date Description Inspector Results Comments
11/18/2025 COT - HCPL - Plumbing Intermediate Passed 11-18-25: plumbing intermediate approved.
11/19/2025 COT - HCPL - Plumbing Progress Passed
11/20/2025 BULD - Electrical Clearance Passed 11-20-25: okay to energize Suite 190. ECO clearance issued to TEP.
11/20/2025 COT - HCEL - Electrical Above Ceiling Passed 11-20-25: approved.
11/20/2025 COT - HCEL - Electrical Intermediate Passed 11-20-25: approved.
12/30/2025 COT - HCBU - Building Progress Passed 12-30-25: Suite's 190 & 150 vestibules are okay to tape & texture. Suite 150-vestibule electrical approved.
01/08/2026 COT - HCEL - Electrical Progress Passed 1-8-26: approved.
01/08/2026 COT - HCME - Mechanical Intermediate Passed 1-8-26: approved.
01/08/2026 COT - HCME - Mechanical Progress Passed 1-8-26: approved.
01/14/2026 COT - FCON - Fire - Final Passed
01/14/2026 ENGR Engineering Final Passed 1/14/25 - unit 190 exterior is complete and safe
01/14/2026 TRSP - ROW - Final/Close-Out Passed
01/14/2026 COT - FCON - Sprinkler - Final Passed Approved on 1/5/26 on permit TF-FCP-0925-00716
01/20/2026 COT - HCBU - Building Final Passed 1-20-26: building final approved.
01/20/2026 COT - HCEL - Electrical Final Passed 1-20-26: electrical final approved.
01/20/2026 COT - HCME - Mechanical Final Passed 1-20-26: mechanical final approved.
01/20/2026 COT - HCPL - Plumbing Final Passed 1-20-26: plumbing final approved.