Permit: TC-COM-0325-00544
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2717 E CORONA RD UNIT 190
Address NEW:
2717 E CORONA RD UNIT 190
Apply Date:
03/18/2025
Applicant:
Avinash Karnati
Description:
REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability. REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP Tenant improvement on existing shell building.
Permit Reviews
Permit Number - TC-COM-0325-00544
Permit Status: Complete
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability.
REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP
Tenant improvement on existing shell building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/26/2026 | APPROVED |
| 05/20/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/20/2025 | APPROVED |
| 04/23/2025 | COMMERCIAL REVIEW - FULL v.2 | 05/13/2025 | REQUIRES RESUBMIT |
| 05/20/2025 | RESTAMP - COMMERCIAL v.1 | 05/28/2025 | APPROVED |
| 03/20/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/16/2025 | REQUIRES RESUBMIT |
| 10/29/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/18/2025 | APPROVED |
| 12/01/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/23/2025 | APPROVED |
| 09/02/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 09/29/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0325-00544
Permit Status: Complete
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability.
REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP
Tenant improvement on existing shell building.
| Date | Description | Comments |
|---|---|---|
| 03/20/2025 | UNIT IDENTIFICATION | |
| 03/20/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/20/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/20/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/20/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00544
Permite Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability.
REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP
Tenant improvement on existing shell building.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2025 | COT - HCPL - Plumbing Progress | N/A | Re-inspection required | 9-15-25: arrived on site at approximately 950am and noted that pour back had already occurred. Therefore, provide a letter to the city for review & approval documenting that pour back at plumbing areas was done per the 2018 IBC and per approved plans. The Letter must be submitted & approved prior to releasing a C of O. |
| 12/03/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 12.3.25 Partial pass for progress areas at top sheet rock fastener areas. Progress at far,I'm also inspected and approved to proceed. |
| 12/23/2025 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 12-23-25: partial pass rough electrical at vestibule. |
| 11/20/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 11-20-25: okay to install ceiling tiles. |
| 10/10/2025 | COT - HCME - Mechanical Progress | N/A | Canceled | 10-10-25: canceled by contractor. |
| 01/14/2026 | COT - FCON - Alarm - Final | N/A | Not Applicable | |
| 01/05/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 1-5-26: pre con meeting. |
| 01/05/2026 | COT - HCEL - Electrical Final | N/A | Canceled | 1-5-26: canceled by contractor. |
| 01/05/2026 | COT - HCME - Mechanical Final | N/A | Canceled | 1-5-26: canceled by contractor. |
| 01/05/2026 | COT - HCPL - Plumbing Final | N/A | Canceled | 1-5-26: canceled by contractor. |
| 01/21/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00544
Permit Description: REV2: Electrical: Sheet E0.1 • Updated the Sheet Index. Sheet E1.3 • Added Lighting Demolition Sheet. Sheet E2.3 • Revised Lighting circuiting and Switching in Warehouse. Sheet E2.6 • Revised Lighting circuiting in Vestibule. Sheet E6.2 • Revised Lighting load on Panel Schedule ‘S150H’. Sheet Response G0. 0 Revised Schedule of Drawings to included E1.3. G0.1 Revised History of Drawings. E1.3 added. G0.2 - G1.0 Demising walls now shown as being built under th eir respective suite permits. A0.1 Door Schedule updated to include vestibule doors. Door hardware group 4 added to schedule to accommodate vestibules . A1.1 – A1.12 Demising walls included under this permit were updated, tagged, and clouded. Vestibules noted and dimensioned. Bollards added around electrical panels and transformers in warehouse . A7.2 Detail 6 added for contractor constructability.
REV1: New layouts, Floor Plan, Charts, calcs, finish schedule, demising wall between gridlines F&E, interior finish, casework, wood doors specs added, MEP
Tenant improvement on existing shell building.
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/18/2025 | COT - HCPL - Plumbing Intermediate | Passed | 11-18-25: plumbing intermediate approved. | |
| 11/19/2025 | COT - HCPL - Plumbing Progress | Passed | ||
| 11/20/2025 | BULD - Electrical Clearance | Passed | 11-20-25: okay to energize Suite 190. ECO clearance issued to TEP. | |
| 11/20/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 11-20-25: approved. | |
| 11/20/2025 | COT - HCEL - Electrical Intermediate | Passed | 11-20-25: approved. | |
| 12/30/2025 | COT - HCBU - Building Progress | Passed | 12-30-25: Suite's 190 & 150 vestibules are okay to tape & texture. Suite 150-vestibule electrical approved. | |
| 01/08/2026 | COT - HCEL - Electrical Progress | Passed | 1-8-26: approved. | |
| 01/08/2026 | COT - HCME - Mechanical Intermediate | Passed | 1-8-26: approved. | |
| 01/08/2026 | COT - HCME - Mechanical Progress | Passed | 1-8-26: approved. | |
| 01/14/2026 | COT - FCON - Fire - Final | Passed | ||
| 01/14/2026 | ENGR Engineering Final | Passed | 1/14/25 - unit 190 exterior is complete and safe | |
| 01/14/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 01/14/2026 | COT - FCON - Sprinkler - Final | Passed | Approved on 1/5/26 on permit TF-FCP-0925-00716 | |
| 01/20/2026 | COT - HCBU - Building Final | Passed | 1-20-26: building final approved. | |
| 01/20/2026 | COT - HCEL - Electrical Final | Passed | 1-20-26: electrical final approved. | |
| 01/20/2026 | COT - HCME - Mechanical Final | Passed | 1-20-26: mechanical final approved. | |
| 01/20/2026 | COT - HCPL - Plumbing Final | Passed | 1-20-26: plumbing final approved. |