Inspection Status: Passed
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2026 |
COT - HCBU - Building Progress |
|
Passed |
1-8-26: approved. |
| 09/26/2025 |
COT - HCBU - Building Progress |
|
Re-inspection required |
9-26-25: add shot pins 12" o.c. at sill and shot pins at top track-see schedule for details. |
| 10/07/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
Sheetrock nailing on West walls. Ok to tape progress areas. |
| 10/08/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
10-8-25: drywall nailing on demising wall from upper decking to approximate 10' AFF verified and approved. Contractor will schedule remaining section of drywall nailing at a later date. Okay to tape & texture progress areas. Framing on suite 150's demising wall and metal framing along fur out inspected and approved. Okay to continue with construction at progress areas. |
| 10/23/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
10-23-25: partial pass on drywall nailing- end of wall still needs drywall. Okay to proceed with tape & texture at progress areas. |
| 10/24/2025 |
COT - HCBU - Building Progress |
|
Canceled |
10-24-25: canceled by contractor. |
| 10/27/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
10-27-25: framing verified per plans. Okay to continue construction at progress areas. |
| 10/30/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
10/30/25 partial pass for drywall pending bathrooms, ok to proceed in suite |
| 11/03/2025 |
COT - HCBU - Building Progress |
|
Not Ready |
11-3-25: not ready. |
| 11/04/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-4-25: okay to tape & texture at restrooms. |
| 11/17/2025 |
COT - HCBU - Building Progress |
|
Not Ready |
11-17-25: not ready |
| 11/18/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-18-25: add stainless steel or galvanized screws for drywall at wet locations in bathrooms. |
| 11/19/2025 |
COT - HCBU - Building Progress |
|
Canceled |
|
| 11/20/2025 |
COT - HCBU - Building Progress |
|
Re-inspection required |
11-20-25: not ready. |
| 11/25/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11/25/2025 partial pass. Screw inspection approved on demising wall. |
| 12/01/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
12-1-25: RFI showing demising wall bracing at 20' o.c. has been submitted to the city for review. Okay to drywall upper section to bottom of decking at own risk. Schedule a screw inspection prior to tape & texture. |
| 12/09/2025 |
COT - HCBU - Building Progress |
|
Canceled |
12-9-25: canceled by contractor. |
| 12/11/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
12-11-25: okay to tape remaining section of drywall. |
| 12/16/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
12-16-25: okay to tape/texture |