Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2026 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
1-8-26: Have architect/engineer of record submit a letter to the city for review documenting relocation of water heater. |
| 01/14/2026 |
COT - HCME - Mechanical Intermediate |
|
Passed |
1-14-26: approved. |
| 10/24/2025 |
COT - HCME - Mechanical Intermediate |
|
Canceled |
10-24-25: canceled by contractor. |
| 10/27/2025 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
10-27-25: partial pass- will check above ceiling after grid is in place. Okay to continue construction at progress areas |
| 11/18/2025 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
11-18-25: fix rips at flex above ceiling on several locations,provide lift to verify framing for HVAC per S3.0 Details 1, 2, 3. |
| 11/19/2025 |
COT - HCME - Mechanical Intermediate |
|
Canceled |
|
| 11/20/2025 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
11-20-25: okay to install ceiling tiles. |