Inspection Status: Canceled
Inspection History: COT - HCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/05/2026 |
COT - HCBU - Building Final |
|
Canceled |
1-5-26: canceled by contractor. |
| 01/08/2026 |
COT - HCBU - Building Final |
|
Re-inspection required |
1-8-26: Have architect/engineer of record submit a letter to the city for review documenting the relocation of water heater. |
| 01/15/2026 |
COT - HCBU - Building Final |
|
Re-inspection required |
1-15-26: install bollard to protect water heater-have architect submit documentation to the city with details, seal penetrations above ceiling at warehouse to office space, provide pictures of labeled junction boxes in warehouse side, adjust interior glass door & warehouse door to office to 5 pounds of pressure, complete installation of drinking fountain and will check water at next inspection. |
| 01/20/2026 |
COT - HCBU - Building Final |
|
Passed |
1-20-26: building final approved. |