Inspection Status: Re-inspection required
Inspection History: COT - LCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 09/08/2026 |
COT - LCPL - Rough Soil |
|
Re-inspection required |
9-8-26: underground plumbing needs to be under test-reschedule when ready. |
| 09/09/2026 |
COT - LCPL - Rough Soil |
|
Partial Pass |
9-9-26: underground plumbing verified under test and per floor plumbing plan-P1.0. Correct number of clean outs together with tracer wire for underground plumbing outside of slab. Okay to backfill using shading materials. |