Inspection Status: Partial Pass
Inspection History: COT - LCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 09/24/2026 |
COT - LCBU - Preslab |
|
Partial Pass |
9/24/2026 Partial pass. Total of 44 spread footers. On grid lines B-E columns 2-12. Approved. Okay for concrete placement. |
| 10/06/2026 |
COT - LCBU - Preslab |
|
Passed |
10/6/26: corrections made ok to proceed with concrete placement |
| 10/06/2026 |
COT - LCBU - Preslab |
|
Re-inspection required |
10/6/26: pre slab it not ready- missing rebar at corners and reinforcement spacing for slab on grade at several areas is not per plans-add reinforcement where spacing is more than 18' o.c., provide a report together with photos with chairs every 4' o.c, a vapor barrier is required at areas having flooring. Reschedule inspection when ready. |