Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2025 | COT - HCBU - Framing | Partial Pass | ||
| 02/24/2025 | COT - HCBU - Framing | Not Ready | ||
| 03/09/2026 | COT - HCBU - Framing | Passed | ||
| 04/01/2025 | COT - HCBU - Framing | Partial Pass | West radius wall and interior shear walls. Approved. Doors 001,002 pending shear walls. Hold downs approved at door openings. okay to cover. 4/1/2025 |
|
| 04/08/2025 | COT - HCBU - Framing | Partial Pass | 4-8-25, framing structural inspection approved. Okay to continue with construction at progress areas.(pending interior TI on Chapel). Admin building #3-drywall nailing-underside of exterior drywall-minus Southwest/and 1 piece at northeast area missing - Rest of verified as per plans(minus conference room #106 sound end not completed due to storefront)okay to tape & texture progress areas. |