Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
02/04/2026 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Canopy 3 electrical pass, rebar, touching form corrected
Canopy 5 Electrical pass, rebar good
Canopy 7 Electrical pass seat, wall, bench, rebar, touching form corrected
Canopy 9 seat wall, Electrical pass rebar, touching form corrected
Canopy 11 seat wall, electrical pass, rebar, touching form corrected. Okay for concrete placement. 2/4/2026
02/26/2026 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
03/09/2026 COT - HCBU - Excavation/Rebar/Zoning  Passed
07/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
09/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Partial approval for elevated stage area line 1.8 - 2.9 / B-C.2 per third party
09/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Partial for staff building masonry wall line 1/D-E, line G/8.5-9 stem wall.
10/20/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
12/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
12/30/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footer inspection approved for canopy 1 support. Total of 4. 2 footers for foundation plan for canopy 13 per detail 501 & 504. Page S2.0 details on S3.0. Total of 6. Reinforcements per plan. Okay for concrete placement. 12/30/2025