Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM04922

Parcel: 11706077R


Addresses:

211 N 4TH AV


Inspection Status: Canceled

Inspection History: COT - HCBU - Building Progress

Permit Number - T22CM04922

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Canceled

Date Description Inspector Results Comments
02/10/2023 COT - HCBU - Building Progress Canceled Contractor cancelled. Will reschedule for 13 February
02/14/2023 COT - HCBU - Building Progress Partial Pass Level #2; Post tension cable system at GL: 10 - 13/K - R. Stair well B, Elevator shaft #4. Ok to place concrete in progress areas.
02/17/2023 COT - HCBU - Building Progress Partial Pass cancel by contractor
02/21/2023 COT - HCBU - Building Progress Partial Pass Masonry pre-grout at Area B water room at 8’ - 12 ‘; B-1 crash wall at 0’ - 4’; B-1 Bike room. Columns CC18A at 7.5/AA; CC18 at 10/N; CC24B at 10.6/N; CC24E at 10.6/P; CC24H at P/10.6. Ok to set forms and place grout and concrete.
02/23/2023 COT - HCBU - Building Progress Partial Pass Columns on level #3: CC24 H at 10.6/Q; CC24J at 10.6/R; CC24K at 11/R; CC23C at 11/Q; CC24G at 14/P; CC24D at 14/N; CC25A at 14/M; CC25 at 14/K; CC23 at 11/O; CC19A at 10/L. OK to set forms and place concrete in progress areas.
02/24/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled. Will reschedule for 27 February.
02/27/2023 COT - HCBU - Building Progress Partial Pass Columns: CC21 at 11/M; CC23D at 12/L, CC23E at13/L. OK to set forms and place concrete.
03/01/2023 COT - HCBU - Building Progress Not Ready
03/03/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled.
03/06/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled.
03/07/2023 COT - HCBU - Building Progress Partial Pass Columns on level #3: C1, C2, C3, B1. OK to set forms and place concrete in progress areas. Level #3, PT Slab L-3P1. Ok to place concrete in progress areas. Masonry pre-grout for North electric room wall at 8’ - 12’. Ok to place grout in progress areas.
03/08/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled, will schedule for 9 March.
03/09/2023 COT - HCBU - Building Progress Partial Pass Level #3 slab at 3 L -P 3. Colorado area, Level #2, pool bottom. OK to place concrete in progress areas.

9 March 2023.
03/15/2023 COT - HCBU - Building Progress Canceled cancelled by contractor
03/16/2023 COT - HCBU - Building Progress Partial Pass PT Cable system at L3P3. Ok to place concrete in progress areas.
03/17/2023 COT - HCBU - Building Progress Partial Pass Shear wall #5 on level #3. Ok to set forms and place concrete in progress areas.
03/21/2023 COT - HCBU - Building Progress Partial Pass Post tension cable system at Level #3, placement #3. Columns at GL: M/8; J/6, J/7, J/8. J/8.5. Ok to set forms and place concrete.
03/23/2023 COT - HCBU - Building Progress Partial Pass Columns at GL: 11/L - Q. Ok to set forms and place concrete. Shear walls at stair core “B”. Ok to set forms and place concrete.
03/27/2023 COT - HCBU - Building Progress Passed Information only; secondary electric at West side of building to be located Northwest to South East.
04/28/2023 COT - HCBU - Building Progress Partial Pass Level #4; shear wall #12. Ok to set forms and place concrete. Level #5 columns at GL: 1/A, 2/A, 3/A, 4/A, 3/B, 4/B, 2/B, 1/B, 1/C, 2/C, 3/C, 4/C. OK to set forms and place concrete in progress areas.
05/01/2023 COT - HCBU - Building Progress Partial Pass Columns on Level #5 at GL: F.8/1, 2/G, 2.4/G.6, 3/G.6, 3/6, 4/G, 6/G, 4.5/F, 4.5/D. Masonry pre-grout at GL: AA/N - L, 11/N -R . Ok to place grout in progress areas. Post tension cable system at Level #5; pour #2. Ok to place concrete in progress areas.
05/03/2023 COT - HCBU - Building Progress Partial Pass Level #5; columns atGL: G.6/6, G/6, G.6/6.6, H/6.6, G.8/6.6, G/7, F/6. OK to set forms and place concrete.
05/04/2023 COT - HCBU - Building Progress Partial Pass Level #5: Columns at GL: C/6, B/6, A/6/, A/7, B/7, B.1/8, C/8, 7/C, 8/F, 7/F. OK to set forms and place concrete. Shear wall #5. OK to set forms and place concrete.

Masonry pre-grout at doggie park area at 0” - 48”; trash room at 9’ 3”, electric/fire room at 9’ 3”. Ok to place grout in progress areas.
05/08/2023 COT - HCBU - Building Progress Passed Level #5, pour #4. Ok to place concrete in progress areas. Level #5; core B, Ok to place concrete in progress areas. Columns on Level #5 at GL; M/6.6, L/6.6, 7/6.6, J/7, J/8. J/8.5, H/8, H/7, L/7/. Masonry pre-grout at Northeast portion of first leave of parking garage of Colorado building.
07/19/2024 COT - HCBU - Building Progress Partial Pass Level #13, rooms 1301 - 1324 for close out inspections
07/22/2024 COT - HCBU - Building Progress Partial Pass Amenities area: Level #3: club room, study room #1, library, dog wash area, spa, 2 bathrooms, fitness room. Level #1: Reception area, offices, break room, 2a restrooms, mail room, storage rooms, bike room.
07/23/2024 COT - HCBU - Building Progress Partial Pass Lightening protection system on roof< need to locate grounding system termination point within building.
07/24/2024 COT - HCBU - Building Progress Passed Lightening protection system complete; terminated in level #1 electric room