Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2024 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Electric clearance to energize systems in main equipment room (MSDB #1 and MSDB #2; Elevator equipment room system MR/G2S, #1, 2, 3 and disconnects. Request for clearance forwarded to Planning and Developement Services at 0845 hours. |
| 04/10/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Electric conduits in slab. #L4 -P5. Ok to cover conduits in proposed slab. |
| 04/14/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Electric conduits on Level #4, pour #2 at 1” - 3”. |
| 05/02/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Inspection should read excavation/rebar and stem wall. Columns at GL: 3/F, 5.5/G, 5.5/F,5/G. Stem wall.at.3’8”on GL: 17, on Level #3, Ok to place concrete in progress areas. |
| 05/15/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Disconnect panels for man-lift. |
| 08/01/2024 |
COT - HCEL - Electrical Progress |
|
Passed |
|
| 08/09/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Level #3, Batch A rooms : 310, 307, 305, 304, 301, 302, 303, 303, 306, 308, 311 |
| 08/14/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Level #3, electric in walls in Batch B of unit rooms, |
| 08/28/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Level #4, Batch C, rooms 427, 428, 423, 425, 426, 430, 432, 431. Batch A, 401, 402, 403, 404, 405, 406, 407, 408, 410, 411. |
| 09/05/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
|
| 11/27/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Sheet rock nailing for room units on Level #7, Area C: 723, 725, 726, 727, 728, 729, 731, 732. Ok to tape and texture progress areas. |