Permit: T22CM04922

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
06/30/2023 COT - HCBU - Framing Partial Pass Level #3, Patch B Area exterior framing. Ok to cover progress areas and water proof sheathing.
07/07/2023 COT - HCBU - Framing Partial Pass Level #3, Batch “C”, exterior framing and sheathing. Level #9, columns at GL: 7/B, 6/C, 7/C, 8/C, 8/B, 8.5/F, 8.5/G, 6.6/G.6, 6.6/H. Masonry pre-grout on Level #3 at GL: R/12 - 15. Ok to grout progress areas; stair well “C” at top out, ok to grout progress areas.
07/17/2023 COT - HCBU - Framing Partial Pass Masonry pre-grout at GL: 11/L at 4’ - 8’, F - G/8.5, L/9 - 10, L/9-11, 15/T - R. OK to place grout in progress areas. Shear walls #11 & #12: ok to set forms and place concrete. Plumbing intermediate: waste and vent lines at 2” - 6” parking area #2 and #3. Room units 301 through 310 with 2” - 4” waste and vent lines, 423 - 432.
08/01/2024 COT - HCBU - Framing Passed
08/07/2023 COT - HCBU - Framing Partial Pass Level #5, Batch “C” exterior walls. Ok to waterproof and cover progress areas. Masonry pre-grout at Stair D (pool room), first lift. Trash room on Level 2, first lift. Ok to grout progress areas.
08/15/2023 COT - HCBU - Framing Partial Pass Level #6, Batch A, exterior framing. Ok to cover progress areas
08/18/2023 COT - HCBU - Framing Partial Pass This inspection is for sheet rock nailing for 4 units on Level #3, Batch A. Ok to tape progress areas.
08/22/2023 COT - HCBU - Framing Partial Pass Level #4, Batch B; domestic water lines at 3/4” - 2”.
08/25/2023 COT - HCBU - Framing Partial Pass Sheetrock nailing: Level #3 rooms: 312, 313, 314, 315. 316. Ok to tape and texture progress areas. Excavation/layout Rebar at Level 12: Shear wall B (Area #5). Vertical columns at GL: 6/A, 6/B, 7/A. OK to set forms and place concrete.
08/31/2023 COT - HCBU - Framing Partial Pass Level #7, Batches A, B, C, D. Exterior framing. Ok to waterproof progress areas.
09/08/2023 COT - HCBU - Framing Not Ready Contractor cancelled, will reschedule for 11 September
09/15/2023 COT - HCBU - Framing Partial Pass Level #4, Batch B rooms and corridor walls for sheet rock nailing. Ok to tape throughout progress areas.
09/19/2023 COT - HCBU - Framing Partial Pass Level #5, MEP’s in rooms 501, 502, 5-3, 504, 505, 506, 507, 508, 5-9, 510, 511.
09/28/2023 COT - HCBU - Framing Partial Pass Level #5, Batch A rooms 501, 502, 503, 504. Ok to tape progress. Masonry pre-grout at Level #3, stairwell D, front wall at 20’ - 24’. Ok to grout progress areas.
10/05/2023 COT - HCBU - Framing Partial Pass Sheetrock nailing on Level #5, Batch B; rooms 513, 514, 515, 516, 517. Ok to tape progress areas.
10/09/2023 COT - HCBU - Framing Partial Pass Level #6, Mechanical, Electrical, Plumbing in rooms 601, 602, 603, 604, 605, 606, 607, 608, 609, 610, 612.
10/13/2023 COT - HCBU - Framing Partial Pass Level #10, Batch B: exterior framing. Ok to cover exterior walls in progress areas.
10/20/2023 COT - HCBU - Framing Partial Pass Exterior framing and sheathing on Level #10, Area A.
10/27/2023 COT - HCBU - Framing Partial Pass 10/27/23: Exterior sheathing and framing Level 11 Areas A,B and C
10/31/2023 COT - HCBU - Framing Partial Pass Sheetrock nailing on Level #6, rooms 625, 626, 627, 628, 629.
11/03/2023 COT - HCBU - Framing Partial Pass Level #14, elevator room; exterior walls. Ok to insulate and cover walls. Level #1, exterior store front walls. Ok to insulate and cover walls.
11/08/2023 COT - HCBU - Framing Not Ready Level #12, exterior framing to be rescheduled for 9 November.
11/16/2023 COT - HCBU - Framing Partial Pass Framing for Level #1, amenities area/restrooms. Ok to cover walls.
11/21/2023 COT - HCBU - Framing Partial Pass 10/27/23: Exterior sheathing and framing Level 11 Areas A,B and C
11/21/23: MFD room framing on first floor per plan ok to proceed.
11/30/2023 COT - HCBU - Framing Partial Pass Sheetrock nailing at Level #8; rooms 801, 802, 803. Level # 5, electric rooms : section A, 546, section B, 541, 544, section C storage room 540. Ok to tape progress areas.
12/06/2023 COT - HCBU - Framing Partial Pass Level #12, Ares A and B: exterior sheathing screw nailing. Ok to cover progress areas.
12/21/2023 COT - HCBU - Framing Partial Pass Level #13, Area B: exterior sheathing and nailing. Sheetrock nailing on Level #8, Area C, unit 831. Ok to tape progress areas.