Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - T22CM04922
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/13/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Level #2 crash wall at GL: 1/A - D at 54”. Water room #B103 CMU walls at 0” - 48”. Ok to place grout in progress areas. | |
02/15/2023 | COT - HCBU - Masonry Pregrout | Canceled | Contractor cancelled. | |
02/21/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU planter walls at 4’ top out on Level #3, East side of building. Ok to place grout in progress areas. | |
02/28/2023 | COT - HCBU - Masonry Pregrout | Not Ready | Contractor cancelled. | |
03/04/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Masonry pre-grout on Level #3 spa/pool area at North end; fire -lace and planters at 0” - 48”. Ok to place grout in progress areas. Level #13 MEP in units 1312, 1313, 1314, 1315, 1316, 1317, 1318 (1319 and 1321 need hangers for,domestic water lines),1320, 1322. Ok to insulate and cover walls. | |
03/08/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Area B, West wall at 0’ - 4 ‘. Ok to place grout in progress areas | |
03/17/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU Crash walls at GL: N/10 - 10.6; 10.6/N - R; R/10.6 - 15.8. Ok to place grout in progress areas. | |
03/22/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU wall at 4’8” - 9’6” at GL: A/2 - 7, Area A, Electric room at GL: J/4.5 - 5.5, J - K/4.5 - 5.5; Stair C at GL: Q/11 - 12. Ok to place grout in progress areas. | |
03/28/2023 | COT - HCBU - Masonry Pregrout | Not Ready | Not ready. Contractor cancelled. Reschedule for 29 March | |
03/29/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU walls at GL: A/1 - 7 at 10’5”; F/8 - 8.5 at 4’. Ok to grout progress areas. | |
03/30/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Excavation/layout rebar: Level #3: columns at GL: 13/L; 13/M, 13/N, L/10. Shear wall #11, Ok to place concrete in progress areas. | |
04/03/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU wall at GL: A/2 - 7, topped out. CMU Crash wall at GL: 7/B - C at 0’ - 4’ AFF. Ok to place grout in progress areas. | |
04/05/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU walls at GL: 1/B - C at 8’ - 12’ AFFE; G - J/3 at 8’ - 12’. Ok to place grout in progress areas. | |
04/10/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | C U wall at GL: A.1/C - G.4 at 4’ above floor level. Ok to place grout in progress areas. | |
04/14/2023 | COT - HCBU - Masonry Pregrout | Not Ready | Contractor cancelled. | |
04/17/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Level #3, columns at GL: 6/F, 6/G, 6/G.6, G/6.6, 7/G, 5.5/E, 4.5/E. OK to set forms and place concrete in progress areas. CMU walls at GL; G.6/2.4 - 4.4, G.6/H.9. OK to place grout in progress areas. |
|
04/20/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | CMU walls at GL: N - Q/7, 10.6 - 8/N - Q at 12 feet AFFE. OK to place grout in progress areas. Level #4 columns at GL: B.1/8, 7/A, 6/A, 6/B, 6/C. OK to set forms and place concrete. | |
05/09/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Inspection should read excavation layout/rebar for columns on Level #5 at GL: M.3/6.8, M/7, N/7.5, N/8.5, N/10, M/10, L/10, M/8, L.5/8. Ok to set forms and place concrete in progress areas. | |
05/10/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Level #1: CMU Crash wall at GL: C - G (west wall). CMU walls at Fire pump room, North and East walls, topped out. North CMU wall of bike room, 2nd lift. Trash room CMU Walla at 2nd lift. Ramp area at Stair B; 2nd lift. | |
05/15/2023 | COT - HCBU - Masonry Pregrout | Not Ready | Contractor cancelled. | |
05/17/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Inspection should read: excavation layout rebar for columns on Level #6 at GL; C/1, C/2, C/3, C/4, F/4.5, E/4.5, F.8/1, G/2. OK to set forms and place concrete in progress areas. | |
05/19/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Northwest corner at GL:B/2. Crash wall at GL: E.5 -6/1 -2. Column at 3/F, Shear wall #5. Ok to place concrete in progress areas. | |
08/01/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
08/10/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Level #3, amenities site wall at 4’ - 8’. Ok to grout progress areas. Level #2, crash wall at trash chute area; topped out. Ok to grout progress areas. | |
08/15/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Level #3, amenities area, top out masonry walls. Ok to place grout in progress area. | |
09/22/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | 9/22/23: Stair D East wall second lift 5'4" lift ok to pour. | |
10/03/2023 | COT - HCBU - Masonry Pregrout | Partial Pass | Stairwell D, 4th Avenue side, topped out at 24’8” - 32’. Ok to grout progress areas. |