Permit: T22CM04922

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
01/03/2024 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines at Level #10, Areas B & C, units: 1012, 1013, 1014, 1015, 1017, 1018, 1019, 1020, 1021, 1022, 1023,1025’ 1026, 1027, 1028, 1029, 1030, 1031, 1032.
01/17/2024 COT - HCPL - Plumbing Progress  Not Ready Contractor cancelled, will reschedule for 18 January
01/18/2024 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines on Level 11, Areas A, B, C,
02/01/2024 COT - HCPL - Plumbing Progress  Partial Pass Level #12, domestic water test in units 1201 through 1222.
02/07/2024 COT - HCPL - Plumbing Progress  Not Ready Contractor cancelled, will reschedule for 8 February.
02/28/2024 COT - HCPL - Plumbing Progress  Partial Pass Level #13, domestic water lines pressure testing. Level #13, Sheetrock nailing in units: 1212, 1213, 1214, 1215, 1216, 1217, 1218. Ok to tape progress areas.
05/03/2023 COT - HCPL - Plumbing Progress  Not Ready Contractor cancelled.
06/21/2024 COT - HCPL - Plumbing Progress  Partial Pass Boiler system and recirculating pump lines are in place. Ensure all lines are properly insulated.
08/01/2024 COT - HCPL - Plumbing Progress  Passed
08/14/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #4, waste and vent lines at 2” - 4” in Batch B of unit rooms.
08/18/2023 COT - HCPL - Plumbing Progress  Partial Pass Levels 5A, 6A, 7A waste and vent lines at 1 1/2 “ - 4”: areas under hydro test.
08/22/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #4, Batch B domestic hot/cold water lines at 3/4” - 2”.
08/25/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #4, Batch “B” waste and vents (2” - 4”): 422, 421, 420, 419, 418, 417, 413, 415, 416, 414, 412.
09/01/2023 COT - HCPL - Plumbing Progress  Not Ready Contractor cancelled.
09/06/2023 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines on Level #5, Section A rooms: 501, 502, 503, 504, 505, 506, 507, 509, 510, 511, 508.
09/08/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #5, Areas B & C. Domestic water lines in room units.
09/27/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #6; Batch C, domestic water lines at 3/4” - 2”. Pre-grout at stairwell D main front at 14’8” - 19’ 4”. Ok to place grout in progress areas.
11/14/2023 COT - HCPL - Plumbing Progress  Partial Pass Level #8, domestic water lines throughout all unit rooms. Waste and vent lines (2 1/2” - 4”) on Levels #8 through Level 13 all in Area B.
11/21/2023 COT - HCPL - Plumbing Progress  Partial Pass 11/21/23: waste and Vent under test Area A levels 8-11,
12/20/2023 COT - HCPL - Plumbing Progress  Partial Pass 11/21/23: waste and Vent under test Area A levels 8-11,
12/20/23: waste and vent under test Area A levels 12-13.
12/29/2023 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines on Level #10, Area A: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009.