Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM03955

Parcel: 14044004C

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Permit Number - T22CM03955

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/23/2025 COT - HCBU - Building Progress Partial Pass 1/23/25: panels 32-59 ok to pour
01/28/2025 COT - HCBU - Building Progress Partial Pass 1/23/25: panels 32-59 ok to pour
1/28/25: reinforcement per plan at panel pour 4. Ok to proceed
02/21/2025 COT - HCBU - Building Progress Partial Pass 2-21-25, verified underground plumbing tie in to main located on east side of building 3. Okay to backfill progress areas
05/28/2025 COT - HCBU - Building Progress Partial Pass 5-28-25, mandrel sewer test located for north side on manholes 1-4 approved. Manhole 4-5 will be tested when ready.
05/29/2025 COT - HCBU - Building Progress Partial Pass 1/23/25: panels 32-59 ok to pour
1/28/25: reinforcement per plan at panel pour 4. Ok to proceed
2-21-25, verified underground plumbing tie in to main located on east side of building 3. Okay to backfill progress
5-28-25, mandrel sewer test located for north side on manholes 1-4 approved. Manhole 4-5 will be tested when ready.
5/20/25: air test on the line at the sewer.
10/29/2025 COT - HCBU - Building Progress Passed 10-29-25: approved.