Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM03955

Parcel: 14044004C

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM03955

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/15/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
01/21/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
1/21/25: reinforcement per plan at panels 34-5. Ok to proceed.
01/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
1/21/25: reinforcement per plan at panels 34-5. Ok to proceed.
1/29/25: reinforcement per plan for pour 4. Ok to proceed with concrete placement.
01/31/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
1/21/25: reinforcement per plan at panels 34-5. Ok to proceed.
1/29/25: reinforcement per plan for pour 4. Ok to proceed with concrete placement.
1/31/25: reinforcement per plans at fire pump room footing.
02/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
1/21/25: reinforcement per plan at panels 34-5. Ok to proceed.
1/29/25: reinforcement per plan for pour 4. Ok to proceed with concrete placement.
1/31/25: reinforcement per plans at fire pump room footing.
2/14/25: reinforcement per plan at west end ramps for concrete setting pad footing for tilt up panels at ramps.
02/21/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2-21-25, verified rebar tie for detail 103B on west end of building 3.
03/17/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.
1/15/25: reinforcement per plan at panels 79-94, 1-10. Ok to proceed.
1/21/25: reinforcement per plan at panels 34-5. Ok to proceed.
1/29/25: reinforcement per plan for pour 4. Ok to proceed with concrete placement.
1/31/25: reinforcement per plans at fire pump room footing.
2/14/25: reinforcement per plan at west end ramps for concrete setting pad footing for tilt up panels at ramps.
2-21-25, verified rebar tie for detail 103B on west end of building 3.
3/17/25: reinforcement per plan at last ramp footing at south west corner of building 3
04/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, reinforcement & vapor barrier per plans for pour back along the edges on east & northeast sections of Building 3. Okay to pour concrete.
05/06/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5-6-25, reinforcement for pour back on Building 3 approved. Okay to pour at progress areas.
10/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed 10-29-25: previously inspected and approved.
11/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/26/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/1/24: reinforcement per plan at continuous footing at GL E/1-18, spread footings per plan at GL B-D/2-8 and B-D/10-17. Ok for concrete placement
11/7/24: Reinforcement per plans at Spread footers at GL A-E/9, continuous footer at GL A/1-18 and 18/A-E per plan ok to proceed.
11/20/24: reinforcement at slab per plan at pour 1 GL 9-13.
11/20/24: reinforcement at slab per plan at pour 3 ok to proceed.
12/3/24: Building 3C Pour 4 Slab on Grade rebar inspection passed.
12/9/24: building 3 pour 5 at slab on grade rebar inspection passed.