Permit: T22CM02222

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Not Ready

Inspection History: COT - LCBU - Building Progress

Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Building Progress Not Ready
07/20/2022 COT - LCBU - Building Progress JBURGE Partial Approval Entered by VVERA1 - Partial. Information for electric under ground line #247.
01/03/2024 COT - LCBU - Building Progress Partial Pass Level #3, Fire caulking around,columns in units 307, 310, 315, 318, 319, 321, 323.
01/10/2023 COT - LCBU - Building Progress Partial Pass Columns on Post Tension Slab at GL: 4.5 - 8/A - D; 3 - 8.5/D - H. 19 total columns; 7 formed and poured, 12 moved down to deck level.
01/11/2024 COT - LCBU - Building Progress Partial Pass Level #10, Area B; Mechanical, Electrical, Plumbing in units 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020, 1021. Ok to cover walls in progress areas.
01/17/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled due to inclement weather.
01/18/2024 COT - LCBU - Building Progress Partial Pass Electric intermediate in units 709, 409.
01/19/2023 COT - LCBU - Building Progress Partial Pass Nevada Area B, columns: CC1, (8 each), CC4, (2 each), CC8, (7 each), CC13, CC14. Shear wall #5 at GL: D -E/6 -7. OK to place concrete in progress areas.
01/23/2023 COT - LCBU - Building Progress Partial Pass Domestic water line from main water line to back-flow preventer (6” to 4”). Ok to cover progress areas.
01/24/2023 COT - LCBU - Building Progress Partial Pass Post tension cable system slab #143. Ok to place concrete in progress areas.
01/25/2023 COT - LCBU - Building Progress Canceled Contractor cancelled.
01/27/2023 COT - LCBU - Building Progress Partial Pass Grade beams in Area C: #6, 8, 9, 16, 17, 22, 23 at GL: K - L.5/9 - 12; L.5 - N.5/ 5.7 - 8; K - R. Ok to place concrete in progress areas.
01/29/2024 COT - LCBU - Building Progress Partial Pass Level #11, Area A; MEP for units 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111. OK to cover walls.
02/01/2023 COT - LCBU - Building Progress Canceled Contractor cancelled. Will reschedule for 2 February
02/01/2024 COT - LCBU - Building Progress Partial Pass Level #4, Fire caulking at exterior columns in units 406, 407, 411, 412, 413, 415, 416, Units #410 and 419 are not ready.
02/03/2023 COT - LCBU - Building Progress Partial Pass Level #2, stairs #A, shear wall: rebar in place. Ok to set forms and place concrete in progress areas. (107 - 122).
02/07/2023 COT - LCBU - Building Progress Canceled Contractor cancelled. Will be reschedule for 8 February
02/08/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled. Will reschedule for 9 February.
02/09/2023 COT - LCBU - Building Progress Partial Pass Post tension cable system on Level #2, GL: G.6 - N.3/4.3 - 10.2. Ok to place concrete in progress areas.
02/12/2024 COT - LCBU - Building Progress Partial Pass Level #12, MEP in units 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211. Sheet rock nailing in lounges on levels #9, 8, 7, 6. Ok to tape progress areas.
02/16/2024 COT - LCBU - Building Progress Partial Pass 9/22/23: Domestic water Level 6 Area B rooms 612,613,614,615,616 under pressure.
10/18/23:Domestic water Level 7 Area B rooms 712,713,714,715,716,717,718,719,720,721 under pressure. 722 pending will be checked with batch C. Waste and vent area C floors 8,9,10,11 all under test.
2/16/24: level 6 fire caulk inspection will be rescheduled for next week.
02/22/2024 COT - LCBU - Building Progress Not Ready Contractor cancelled, will reschedule for 23 February.
02/27/2024 COT - LCBU - Building Progress Partial Pass Level #13, Area A: MEP for units 1301 through 1311. OK to cover walls in progress areas. Domestic water lines in Area A, units 1301 through 1311.
03/10/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
03/14/2023 COT - LCBU - Building Progress Partial Pass inspection only
03/29/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
04/05/2023 COT - LCBU - Building Progress Partial Pass Post Tension Cable System at Level #3; pour #5. Ok to place concrete in progress areas.
04/07/2023 COT - LCBU - Building Progress Partial Pass Columns on Level #2 at GL: 14/L, 15/L, 15/M, 16/L, 17/L, 17/M.3, 15/G, 14/Q, 14/R/ 15/R. Ok to set forms and place concrete. Masonry pre-grout at GL: AA - E/ South-west. Ok to place grout in progress areas. Post tension cable system on Level #3, pour #5. Ok to place concrete when electric has been completed.
04/11/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at GL; A.2 - H.4. Second lift above finished flppr
04/11/2024 COT - LCBU - Building Progress Partial Pass Landings in stairwell “B”, Levels #1 - 13; framing is Ok to Sheetrock progress areas. Garage Levels #1 & #2 fresh air returns and fans, duct systems, condensation lines for wall units for equipment rooms and electric rooms.
04/12/2023 COT - LCBU - Building Progress Partial Pass Level #4, Columns at GL: 2/C, B/1, A/1, A/2, B/2, B/3, A/3, A/4, B/4, 3/C, 7/C, 8/C. OK to set forms and place concrete in progress areas.
04/14/2023 COT - LCBU - Building Progress Partial Pass Level #4, pour #2: Post Tension Cable system. Columns on Level #4 at GL: B/3, B.6/2.4, B.6/3, B.6/4, B.6/5, F/5.5. Level #4: Stair core “C”. Ok to place concrete in progress areas.
04/18/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
04/21/2023 COT - LCBU - Building Progress Partial Pass Level #4; columns at GL: J/6.6, J/7, J/8.5, J/8, K/6.6, K/7, M/6.6, M/8, L.5/8. OK to set forms and place concrete in progress areas.
04/24/2023 COT - LCBU - Building Progress Partial Pass Columns on Level #4 at GL: U/F, 6.8/M.3, 7.5/N, N/8.5, 10.0/M, 10/L. OK to set forms and place concrete. Shear wall on stair core B. Ok to set forms and place concrete.

Post tension cable system on Level #4; pour #5. Ok to place concrete in progress areas.
04/25/2023 COT - LCBU - Building Progress Partial Pass CMU Walls at 14’ 2” at GL: N - R/8.5 - 11. Ok to -lace grout in progress areas.
04/26/2023 COT - LCBU - Building Progress Partial Pass Columns on Level #4, pour 5 area. Ok to set forms and place concrete at GL: 11/L, 10/M, 11/N, 12/L, 13/L, 13/M. Post tension cable system at Level #5; pour #1. Ok to place concrete in progress areas.
05/22/2023 COT - LCBU - Building Progress Partial Pass Excavation/layout rebar; Level #6, columns at GL: 8/F, 7/F, 7/C, 6/C, 6/B, 6/A, 7/A, 7/B, 8/B, 8/C, 6/G.6. Shear wall LB6/Elevators #3 & 2. Post tension cable system slab at Level #6, pour #4. OK to set forms and place concrete in progress areas.
05/24/2023 COT - LCBU - Building Progress Partial Pass Level #6, columns at GL: H/8, H/7, J/8, L/7, L/6.6, M/6.6, M/7, 6.8/M.3, N/7.5. Shear wall LB-7, #11, shear wall #12. OK to set forms and place concrete.
05/25/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at GL: F-B/8, B/2 (topped out). Level #6, columns at GL: 11/M, 10/N, 10/M, 11/P, 11/N, 11/N.7, 12/L, H/6.5, 5/H-L. OK to set forms and place concrete in progress areas.
05/26/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout, CMU walls at 4’ - 8’ on GL: B/2, D/8-9 at 8’ 8”, North mailroom wall at 4’8”. Ok to place grout and concrete in progress areas.
05/30/2023 COT - LCBU - Building Progress Partial Pass Columns on Level #6, Pour #4, at GL: 13/L, 13/M, 12/M, 13/N, 13/P, 13/Q, 12/Q, 11/Q. OK to set forms and place concrete.
05/31/2023 COT - LCBU - Building Progress Partial Pass Level #7, pour #2; columns at GL: 1/A, 2/A, 3/A, 4/A, 1/B, 2/B, 3/B, 4/B, 3/C, 4/C. OK to set forms and place concrete.
06/01/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at GL: 8.5/E.5 - F at 4’8’. Ok to place grout in progress area. Excavation/layout rebar; columns at Level 7, Area A: GL: 1/C, 2/C, 1/F.8, 2/G, 3/G, 4/G, 2.4/G.6, 3/G.6, 4/G.6. 3/G.6, 4/G.6, 5/G.6,3/G, 4/G, 5/G, 4.5/G. OK to set forms and place concrete in progress areas. Level #7. pour #2 Post Tension,Cable system. Ok to place,concrete in progress area.
06/02/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
06/05/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at North mailroom at 8’ - 12’. Ok to place grout in progress areas. Post tension cable system at Level #7, placement #3. Ok to place concrete in progress areas. Level #7 columns at GL: 3/F, 4.5/F, 4.5/E, 5.5/E, 5.5/F, 6/F, 7/F, 7/G, 6.6/G.6, 8/G, 6/A, 6/B, 6/C, 7/A, 7/B, 7/C, 8/B, 8/C
Level #7, shear wall #5. Ok to set forms and place concrete.
06/06/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
06/07/2023 COT - LCBU - Building Progress Partial Pass Level #7. columns at GL: F/8, 8/C; Ok to set forms and place concrete in progress areas. Stairway #B at Level #7. Ok to set forms and place concrete in progress areas. Level #7, pour #3. Ok to place concrete in progress areas.
06/08/2023 COT - LCBU - Building Progress Partial Pass Grade beams #7, #10, #10 at GL:14 - 17/L -M. Ok to place concrete in progress areas. Level #7 columns at GL: J/7, J/8, 6.6/K, 7/K, 6.6/M, 6.8/M.3, 7/M. OK to set forms and place concrete in progress areas.
06/09/2023 COT - LCBU - Building Progress Partial Pass CMU masonry walls at GL: (8/C-D, crash wall), stairwell B North wall, top out on Level #1. Ok to place grout in progress areas. Level #7, columns at GL: 10/L, 10/M, 8/L.5, M/8. OK to set forms and place concrete.
06/12/2023 COT - LCBU - Building Progress Partial Pass Level #7 columns at GL: 11/L, 11/M, 11/N, 11/N.7, 11/P, 11/8, 12/Q, 12/K, 12/M, 13/L, 13/M, 13/N, 13/P, 13/Q. Ok to set forms and place concrete. Shear walls #11 and #12. Level #8, concrete placement #1. Ok to place concrete in progress areas.
06/13/2023 COT - LCBU - Building Progress Not Ready Will reschedule for 14 June 2023.
06/15/2023 COT - LCBU - Building Progress Partial Pass CMU Walls at GL: 8/A - B, 8.5/B -F on Level #2. Ok to place grout in progress areas. Framing: Level #3: Batch A exterior framing. Ok to cover exterior walls. Excavation/layout rebar: grade beam at GL: 17/L - R, 15 - 17/R. OK to place concrete in progress areas. Columns on Level #7 at GL: 1/A, 2/A, 3/A, 4/A, 4/B, 3/D, 1/A, 2/B, 3/B, 3/C, 4/C, 2/C, 1/C, 1/F.8, 3/F, 2/G, 2.4/G.6, 3/G.6, 4/G.6, 5/G.6, 3/G, 4/G. OK to set forms and place concrete in progress areas. Level #8, slab pour #2. Ok to place concrete in progress.
06/16/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at garage level crash walls, GL: 6/E - B.1, 6/A - B, B/7 - 8. Storage room 206, elevator lobby, exterior wall at 6.6 - 8/2M. Ok to place grout in progress areas.
06/20/2023 COT - LCBU - Building Progress Partial Pass Excavation/layout rebar ar Level #8; Shear wall #5. Ok to set forms and place concrete. Columns on Level #8 at GL:6/A, 6/B, 7/A, 7/B, 8/B, 8/C, 8/F, 7/F, 8.5/F, 8.5/G, 8/G, 7/G, 8.5/H, 8/H, 6.6/H, 7/H, 8.5/G. OK to set forms and place concrete. Masonry pre grout for concrete masonry walls at GL: 15/M - R, R/15 -11, B -D/7, A -B/B/7 -8, 8 -9/N.7 - M.3. Ok to grout progress areas.
06/21/2023 COT - LCBU - Building Progress Partial Pass Excavation/layout rebar: Level #8, stairwell A. Ok to set forms and place concrete. Pre-slab at Level #8, pour #3. Ok to place concrete in progress areas.
06/23/2023 COT - LCBU - Building Progress Partial Pass Level #8 columns at GL: 6.6/J, 7/J, 8/J, 8.5/J, 7/L, 6.6/L, 6.6/M, 7/M, 6.8/M.3, 7.5/N, 8.5/N, 10/N, 11/N, 10/M, 10/L, 11/L, 11/N, 12/L, 12/M, 13/L, 13/M, L/5, 8/N. OK to set forms and place concrete in progress areas.
06/26/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at Level #2, stair well “C”; 0” - 48”. North crash wall at 48” top out (14 - 17/L. Ok to place grout in progress areas. Columns at Level #8: 13/N, 13/P, 13/Q, 12/Q, 11/Q, 11/P,11/N.7. OK to set forms and place concrete in progress areas. Shear walls #11 and #12; Ok to set forms and place concrete.
06/27/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
06/28/2023 COT - LCBU - Building Progress Partial Pass
06/29/2023 COT - LCBU - Building Progress Partial Pass Level #9 columns at GL: A/1, A/2, A/3, A/4, B/4, B/3, B/2, B/1, C/2, C/1, G/3, G.6/3, G.6/4. OK to set forms and place concrete in progress areas.. Level #9, Post tension cable system at slab #2. Ok to place concrete in progress areas.
07/05/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout, CMU wall at 4’8” on GL: R/12 - 15. OK to grout progress area. Level #9, columns at 1/F.I, 2/G, 2.4/G.6, 3/G.6, 4/G, 3/F, F.5/E, F.5/F, 5.5/E, 5.5/F, 6/F, 6/E, 6/G.6, G/6.5, G/5, 7/G, 8/G, 7/F. OK to set forms and place concrete.
07/06/2023 COT - LCBU - Building Progress Partial Pass Level #9; columns at GL: 7/A, 6/A, 6/B, Ok to set forms and place concrete. Level #9 Post Tension Cable system at pour #3. Ok to place concrete in progress areas.
07/10/2023 COT - LCBU - Building Progress Partial Pass Level #9, stairwell B, shear walls. Ok to place concrete in progress areas. Level #9 columns at GL: 7/H, 8.5/H, 8/H, 6.6/J, 7/J. OK to set forms and place concrete in progress areas. Masonry pre-grout at,Level #3, GL: 12 - 17/ R -K. Ok to place grout in progress areas.
07/12/2023 COT - LCBU - Building Progress Partial Pass Level #9: slab #9, pour #4. Ok to place concrete in progress areas. Level #9: Columns at GL: 6.6/K, 7/K, L/8, M/8, 7/M, L.5/8, 6./M, 6.8/M.3, 7.5/M, 10/N, 10/M, 10/L. OK to set forms and place concrete. Exterior framing on Level #4, Batch B. Ok to cover progress areas.
07/13/2023 COT - LCBU - Building Progress Partial Pass Level #9, Columns at GL: 8.5/N, 11/L, 11/M, 11/N, 12,L,13/L, 12/M, 13/M, 14/N, 13/P, 13/Q. OK to set forms and place concrete. Excavation/layout rebar at GL: R/15.8 - 14
07/14/2023 COT - LCBU - Building Progress Partial Pass Exterior framing at Level #4; Batch B. Ok
to cover.progress areas. Excavation/Layout rebar at Level #3, concrete curb at GL: 10.5/N - R. Post tension cable system at Level #10, pour #1. Ok,to,place concrete in progress areas.
07/15/2024 COT - LCBU - Building Progress Passed
07/18/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
07/19/2023 COT - LCBU - Building Progress Partial Pass Masonry pre-grout at Level #3, 18’8” - 22’4” on GL: R/14 - 17. Ok to grout progress areas. Columns on Level #10 at GL: 1/A, 2/A, 1/B, 2/B, 3/A, 3/B, 4/A, 4/B, 1/C, 2/C, 3/C, 4/C, 3/F, 2/G. Ok to set forms and place concrete. CMU shear walls at stairwell A.
07/20/2023 COT - LCBU - Building Progress Partial Pass Level #10 columns at GL: 1/F.8, 2/G, 2.4/G.6, 3/G, 3/G.6, 4/G, 4/G.6, 5/G, 5/G.6, 4.5/E, 4.5/F, 5.5/E, 5.5/F. OK to set forms and place concrete.
07/21/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
07/24/2023 COT - LCBU - Building Progress Partial Pass Level 10 columns at GL: C/7, C/6, 6/B, A/6, 7/A, 7/B, 8/B.1, 8/F F/8.5, 7/F, 6/F, 6/G.6, 6/G.6, G/8.5, G/8, 7/G. Shear wall #5. Level #10: slab at Level #10, pour #3 of Post Tension cable system. Ok to place concrete in progress areas.
07/26/2023 COT - LCBU - Building Progress Partial Pass Level #3, Room 309; pre-inspection electric walk through.
07/28/2023 COT - LCBU - Building Progress Partial Pass Plumbing intermediate (domestic water lines) at Batch B rooms 312, 313, 316, 317, 319, 320. Batch A, rooms 301, 303D, 305, 307, 309.

Level #10; placement #4: columns at GL: 10/M, 10/N, 10/L, 8.5/N, 11/L, 11/M, 12/L, 12/M, 13/L, 13/M, 13/N, 13/P, 13/Q. OK to set forms and place concrete in progress areas.
08/02/2023 COT - LCBU - Building Progress Partial Pass Level #3, domestic water lines in area B: 301, 313, 314, 315, 316, 317, 318, 319, 321, 322. Room in area C: 323, 326, 325, 327.
08/21/2023 COT - LCBU - Building Progress Partial Pass Level #3, Batch C, rooms 325, 326, 327 Mechanical intermediate and Electric intermediate.
08/22/2023 COT - LCBU - Building Progress Partial Pass Level #12, vertical columns and stair well, inspection performed by special inspector.
08/24/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
08/29/2023 COT - LCBU - Building Progress Partial Pass Level #12, vertical columns at GL: C/U, D/7, A.5/D1, 8/D, 8/F, 8.5/F, 8/G, 7/D. Sheetrock nailing at Level #3, Area B, rooms 321, 319, 313, 316, 317, 318, 320. Waste and vent lines (2” - 4”) on Level #5, 6, 7 in Area B.
08/30/2023 COT - LCBU - Building Progress Partial Pass Excavation/layout rebar: Level #12: Stairwell B; columns at GL: 7.5/N, 8/M, L.5/8, J/6.6, J/7, H/6.6, H/7, H/8, H/8.5, G/8.5. OK to set forms and place concrete in progress areas.
09/01/2023 COT - LCBU - Building Progress Partial Pass Level #13, placement #2. Ok to place concrete in progress areas. Level #3, room #323, mechanical, electric, plumbing rough in.
10/12/2023 COT - LCBU - Building Progress Partial Pass Level #5 unit rooms: 517, 518, 519, 520, 521, 522, 527: Sheetrock nailing, Ok to tape throughout.
10/17/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled.
10/18/2023 COT - LCBU - Building Progress Partial Pass 9/22/23: Domestic water Level 6 Area B rooms 612,613,614,615,616 under pressure.
10/18/23:Domestic water Level 7 Area B rooms 712,713,714,715,716,717,718,719,720,721 under pressure. 722 pending will be checked with batch C. Waste and vent area C floors 8,9,10,11 all under test.
11/03/2023 COT - LCBU - Building Progress Not Ready Contractor cancelled Sheetrock nailing on Level #12. Will reschedule for 6 November.
11/06/2023 COT - LCBU - Building Progress Partial Pass Level #7, Mechanical, Electrical, Plumbing in rooms 712, 713, 715, 717, 718, 719, 720 721, 722.
11/08/2023 COT - LCBU - Building Progress Partial Pass Level #14 pour back. Ok to place concrete pending structural engineer’s final approval. Level #6, mechanical, electrical and plumbing in room 623. Ok to cover walls.
11/13/2023 COT - LCBU - Building Progress Partial Pass Level #7, mechanical, electrical, plumbing in rooms; 723, U25, 726, 727, 728,729, 70, 732, 732. OK to cover walls in progress areas.
11/20/2023 COT - LCBU - Building Progress Partial Pass Level #8, Mechanical, Electrical, and Plumbing in rooms 801, 802, 803, 804, 805, 806, 807, 808, 809, 810, 811. Ok to insulate and cover walls
12/04/2023 COT - LCBU - Building Progress Partial Pass Level #8, Mechanical, Electric, Plumbing in rooms: 823, 825, 826, 827, 828, 829, 831, 832. Level #6 corridors above ceiling, except for East and Southeast portions.
12/07/2022 COT - LCBU - Building Progress Partial Pass 12/05/22.
rebar wall row 8.5, columns F to G. rebar columns, row R, columns 10.6, 11, and 12. Rowe N8.5, 10, 11. Row M, 6.6. Row M, 10.

12/06/22
plumbing underground. From south east corner to grease trap interceptor, from grease interceptor go south to grid line 13 then go west 75 feet.

12/07/22.
rebar columns grid lines A,6. A,5. L, 10. M, 6.3. M, seven. M .3, 6.8. Q, 11. Q, 12.
stairwell A, basement level for elevator approximately 6 foot height pour.
plumbing rough. North Nevada storm drains.
12/07/2023 COT - LCBU - Building Progress Partial Pass Level #6; corridors above ceiling. Lounge rooms at levels #4, 6, 7 at rooms 443, 643, 743.
12/11/2023 COT - LCBU - Building Progress Partial Pass Level #9, Area A: Electric, Mechanical, Plumbing in units 9-1, o02, 9-3, 905, 906, 907, 908, 909, 910, 911.
12/13/2022 COT - LCBU - Building Progress Partial Pass Columns: CC1-H at GL: 8.5/F; CC24 at GL: 10.6/Q. Retaining wall at GL: 1/B - C; 1/D.8 - F.1. Ok to place concrete in progress areas.
12/15/2022 COT - LCBU - Building Progress Partial Pass Electric underground conduits 8 lines at 3” on East central portion of the Colorado area. Ok to cover progress areas.
12/28/2022 COT - LCBU - Building Progress Canceled Contractor cancelled; rained out. Will reschedule for 29 December.
12/30/2022 COT - LCBU - Building Progress Partial Pass Stem wall at GL: 15/M - R; 15 - 14/M; 14/K - M. Rebar for stair A at 1 - 2/C.3 - E.3. Ok to place concrete in progress areas.