Permit: T22CM02222

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Not Ready

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning  Not Ready
08/11/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Retaining walls at elevator pit area to Southeast corner area. Ok to shotcrete progress and area.
07/26/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Three caisson footings and cages at SOUTHEAST corner of NEVADA section.
07/20/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. Retaining wall at West and North areas (#4 rebar and #4 wire mesh). Ok to shotcrete progress areas.
07/14/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Colorado section retaining walls at Southwest to South (15’ soil nails); South to East retaining walls (28’ soil nails). Ok to shotcrete progress areas.
07/08/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. Nevada section; stem wall rebar at West Northwest, and North stem walls. Progress areas have been covered with shotcrete.
06/24/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Approximately 50 GEOPIERS in phase 1 area
11/04/2022 COT - LCBU - Excavation/Rebar/Zoning  Not Ready Not ready. Contractor cancelled. Will reschedule for 7 November.
11/09/2022 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Concrete wall at GL: H - H.9/4.4; H/6. Crash wall at GL: 5 - 7/G.5; column CC30 at GL: 4.4/G.6. Ok to place concrete in progress areas.
11/22/2022 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Columns CC1 at H/8.5, CC1A at G/3, CC2 at 2/A, CC5 at 2/B, CC2 at A/3, CC5 at B/3, CC2 at 1/C, CC5 at C/2, CC2 at C/4, CC1 at D/5.5, CC7 at F.8/1. Wall footings at 8.5/J-K, L/7.5-8. Column footings CF-4 at 10.6/P, CF12 at N/10, CF9.6 at L/11, CF12.6 at9/N, CF14.6 at 11/L.5. Ok to place concrete in progress areas
11/23/2022 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Shear wall #5 at GL: D/6 - 7; shear wall #12 at GL: Q/11 - 12. Column footing CF1–OA. Column CC12 at D/5; CC12A at D/4; CC8 at J/4.5; CC8 at 4.9/AA; CC8 at K/5.5. Ok to place concrete in progress areas.
11/28/2022 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Inspections to be performed by special inspection until further notice.
07/12/2023 COT - LCBU - Excavation/Rebar/Zoning  Passed