Inspection History: COT - HCBU - Building Progress
Permit Number - T22CM02219
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/04/2024 | COT - HCBU - Building Progress | Partial Pass | Mechanical, electrical, and Plumbing for units 1001 - 1011 on Level #10, Area A. Ok to Sheetrock walls. | |
01/10/2024 | COT - HCBU - Building Progress | Partial Pass | Electric intermediate in Electric rooms: 1041, 1044, 1141, 1144. Ok to cover walls,in progress areas. | |
01/16/2024 | COT - HCBU - Building Progress | Not Ready | Contractor cancelled, will reschedule for 17 January | |
01/22/2024 | COT - HCBU - Building Progress | Partial Pass | Level #13, Electric rooms at 1341 and 1344. Level #10 Mechanical, Electrical, Plumbing in units 1028, 1030, 1031, 1032. Ok to cover walls. | |
01/24/2024 | COT - HCBU - Building Progress | Not Ready | Contractor cancelled, will reschedule for 25 January | |
01/29/2024 | COT - HCBU - Building Progress | Partial Pass | Level #11, Area A: MEP for units 1101, 1102, 1103, 1104, 1105, 1106, 1!07, 1108, 1109, 1110, 1111. OK to cover interior walls. | |
01/31/2024 | COT - HCBU - Building Progress | Partial Pass | Level #9, corridors above ceiling: Mechanical, electrical, plumbing. Ok to install ceiling grid in progress areas. | |
02/05/2024 | COT - HCBU - Building Progress | Partial Pass | Level #11, Areas A & B; Mechanical, Electrical, Plumbing in units: 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121, 1122, 1123. Ok to insulate and cover walls and ceilings. | |
02/14/2024 | COT - HCBU - Building Progress | Partial Pass | Level #11, Area A Sheetrock nailing in units 11-5, 1106, 1107, 1110, 1111. Ok to tape progress areas. Level #5 Fire caulking at columns in units 501 - 507. Units need to be rechecked to ensure proper caulking. | |
02/20/2024 | COT - HCBU - Building Progress | Partial Pass | Level #12; MEP in units, 1202, 1203, 1214, 1215, 1216, 1217, 1218, 1219, 1220 1221. Units 1222 and 1223 were not,ready for inspection. NOTE: Level #10 above ceiling is,not ready for inspection due to numerous corrections needed. | |
02/26/2024 | COT - HCBU - Building Progress | Not Ready | Contractor cancelled, will reschedule for 27 February. | |
03/01/2024 | COT - HCBU - Building Progress | Partial Pass | Level #1, amenities area, offices, bike room above ceiling. Level #3, amenities areas, offices, gym area above ceiling. | |
03/05/2024 | COT - HCBU - Building Progress | Not Ready | Elevator fronts framing are not ready. Fire caulking is incorrect. | |
03/06/2024 | COT - HCBU - Building Progress | Partial Pass | Level #13, MEP in unit #1321. Sheetrock nailing in units : 1301, 1302, 1303, 1304, 1305, 1306, 1307, 1308, 1309, 1311. Ok to tape progress areas. Elevator face framing Fire caulking at levels #1 - #8. | |
03/07/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled, will reschedule for 8 March. | |
03/08/2024 | COT - HCBU - Building Progress | Partial Pass | Elevator fronts, Fire caulking on levels 9 - 13 and level #1. | |
03/13/2024 | COT - HCBU - Building Progress | Partial Pass | Trash chutes with fire sprinkler heads and supply water lines in trash rooms on levels 13, 11, 9, 7, 5, 3. | |
03/14/2024 | COT - HCBU - Building Progress | Partial Pass | Level #13 sheet rock nailing in units: 1313, 1314, 1315, 1316, 1317, 1318, 1319. Ok to tape progress areas. | |
03/15/2023 | COT - HCBU - Building Progress | Partial Pass | Inspection is for masonry pre-grout at GL: 8/J - N.7 at 0” - 48” AFFE. Ok to place grout in progress areas. Excavation/layout rebar: Slab L3P2 ; 20 columns have been dropped. Ok to set,forms and place concrete in progress areas. | |
03/15/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled inspection, will reschedule for 18 March. | |
03/18/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. Will reschedule for 19 March. | |
03/19/2024 | COT - HCBU - Building Progress | Not Ready | Level #11, corridor above ceiling trades; not ready as per Jason. Will reschedule. | |
03/20/2024 | COT - HCBU - Building Progress | Partial Pass | Level #13, Sheetrock nailing in units 1318, 1319, 1320, 1321, 1322, 1323. Ok to tape progress areas. Level #11 over head MEP in corridors. | |
03/21/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled, will reschedule for 25 March. | |
03/25/2024 | COT - HCBU - Building Progress | Partial Pass | 10/11/23: Domestic Water level 7 Area A under test ok to proceed. 11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed. 3/25/24: no inspection needed |
|
03/26/2024 | COT - HCBU - Building Progress | Partial Pass | Sheet rock nailing in unit #1322; two hour fire covering for interior steel beam | |
03/27/2024 | COT - HCBU - Building Progress | Partial Pass | Level #3 corridors above ceiling. Ensure All penetrations are properly Fire caulked. | |
03/28/2024 | COT - HCBU - Building Progress | Partial Pass | Level #12, corridors above ceiling. Ensure all penetrations are properly Fire caulked. | |
04/01/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled, will reschedule for 2 April | |
04/02/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled inspection. | |
04/03/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
04/04/2024 | COT - HCBU - Building Progress | Partial Pass | Stairwell “C”, interior framing. Ok to insulate and sheet rock walls. | |
04/05/2024 | COT - HCBU - Building Progress | Partial Pass | Information only; in-fill,in buck-hoist area. | |
04/08/2024 | COT - HCBU - Building Progress | Partial Pass | Level #13, Mechanical, Plumbing, Electric above ceiling. | |
04/09/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
04/16/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
04/17/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
04/18/2024 | COT - HCBU - Building Progress | Partial Pass | Information only; in- fill framing in buck hoist area (scheduling). | |
04/19/2024 | COT - HCBU - Building Progress | Partial Pass | Requested location,for emergency generator disconnect. Disconnect to be located on column at left side of generator. | |
04/22/2024 | COT - HCBU - Building Progress | Canceled | Contractor canceled | |
04/23/2024 | COT - HCBU - Building Progress | Partial Pass | Exterior sheathing at in fill units (buck hoist areas) at Levels 3 - 13. Ok to waterproof progress areas. | |
04/24/2024 | COT - HCBU - Building Progress | Partial Pass | Levels #12 and #13, above ceilings in,corridors. Ok to set ceiling grid and Sheetrock. Unit rooms 324, 424, 524, electric and plumbing. Mechanical to be installed. | |
04/26/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled: units not ready on levels 9 - 13. Will reschedule for 29 April | |
04/30/2024 | COT - HCBU - Building Progress | Partial Pass | Framing, plumbing, and electric in units 1324, 1224, 1124, 1024, 924. Domestic water lines in units 1324, 1224, 1124, 1024, 924, 824, 727, 624, 524. | |
05/05/2023 | COT - HCBU - Building Progress | Partial Pass | Level #5; pour #3 of Post Tension Cable system. Ok to place concrete in progress areas. Columns on Level #5: GL: H/8.5, G/8.5, F/8.5. Ok to set forms and place concrete in progress areas. | |
05/06/2024 | COT - HCBU - Building Progress | Partial Pass | Fire caulking at elevators on Levels 8, 11, 12, 13. Ok to insulate and Sheetrock. Sheet rock nailing in units 824, 924. Ok to tape progress areas. | |
05/07/2024 | COT - HCBU - Building Progress | Partial Pass | Sheet rock nailing in rooms 1024, 1124, 1224, 1324. Ok to tape progress areas. | |
05/08/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
05/11/2023 | COT - HCBU - Building Progress | Partial Pass | Level #5: columns at GL: 11/L, 12/L, 13/L, 11/M, 12/M, 13/M, 11/N, 12/Q, 13/N, 11/N7, 11P, 13/P; 11/Q. OK to set forms and place concrete in progress areas. Masonry pre-grout at GL: 14/M - R, Southeast garage area at ramp, 9.5, CMU Wall at N/8 - 10 at 48”. Ok to place grout in progress areas. | |
05/13/2024 | COT - HCBU - Building Progress | Partial Pass | Elevator lobby areas above ceilings at Levels #3 through Level 13. | |
05/15/2024 | COT - HCBU - Building Progress | Canceled | ||
05/16/2023 | COT - HCBU - Building Progress | Partial Pass | Excavation layout and rebar: Level #6, stair C. Columns at GL: B/1, A/1, A/2, A/3, A/4, B/2, B/3, B/4. Masonry pre-grout at corner Northwest at B/2. Crash wall at N/7 - 10.3. Ok to place grout in progress areas. | |
05/16/2024 | COT - HCBU - Building Progress | Partial Pass | Stairwell “C” sheet rock nailing at Levels #1 - #10. West side of stairwell, walls have been Fire caulked and taped. | |
05/18/2023 | COT - HCBU - Building Progress | Partial Pass | Level #6 slab; pour #3 at 6 -3. Columns on GL: 3/G, 4/G, G.6/2.4, 3/G.6, 4/G.6, 4/G, 5/G.6, 5/G, 6/G, 6/F. OK to set forms and place concrete. | |
05/21/2024 | COT - HCBU - Building Progress | Partial Pass | Stairwell “C” Levels 3 - 13, Sheetrock and Fire caulking . Air pressure duct system 3 - 13. | |
05/22/2024 | COT - HCBU - Building Progress | Partial Pass | Plumbing intermediate at gas line (2”) from Level #10 to roof. Pressure tested. Branch line (1”) to amenities area. | |
05/23/2023 | COT - HCBU - Building Progress | Partial Pass | Level #6 columns at GL: F/8.5, G/8.5, H/8.5, J/8.5, G/6.6, H/6.6, J/6.6. Ok to set forms and place concrete. | |
05/28/2024 | COT - HCBU - Building Progress | Partial Pass | 10/11/23: Domestic Water level 7 Area A under test ok to proceed. 11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed. 3/25/24: no inspection needed 5/28/24: no inspection needed. |
|
05/30/2024 | COT - HCBU - Building Progress | Partial Pass | Sheetrock nailing at elevator lobby’s on Levels 3 - 8. Ok to tape progress areas. Framing: Stairwell “C”, framing for positive air duct system on Levels 3 - 10. Ok to,sheet rock progress areas. | |
06/03/2024 | COT - HCBU - Building Progress | Partial Pass | Stairwell “C” Sheetrock nailing at,levels #5 - 13. | |
06/05/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled; will reschedule. | |
06/10/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
06/11/2024 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
06/26/2024 | COT - HCBU - Building Progress | Partial Pass | Level #4, Room units 401 - 420 close - out inspections. Required corrections submitted to GC. | |
06/27/2024 | COT - HCBU - Building Progress | Partial Pass | Close out room inspections on Level #4: 421, 422, 423, 424, 425, 426, 427, 428, 429, 430, 431, 432. Room unit inspections on Level #5: 524, 525, 526, 527, 528, 529, 530 | |
06/28/2024 | COT - HCBU - Building Progress | Partial Pass | Close - out room inspections at Level #5, Room units: 501 - 523. | |
07/02/2024 | COT - HCBU - Building Progress | Partial Pass | Close out unit inspections at Level 6; 601 - 619, Level 7; 701 -712. | |
07/03/2024 | COT - HCBU - Building Progress | Partial Pass | Level #7, close out unit inspections at 712 - 732. | |
07/08/2024 | COT - HCBU - Building Progress | Partial Pass | Level #8; room units close-out inspection #801 - 832. | |
07/09/2024 | COT - HCBU - Building Progress | Partial Pass | Close-out room inspections at Level #9: #901 - 932. Excavation rebar: 9 light pole caisson footings, ufers are in place. Ok to place cages and concrete in progress areas. | |
07/10/2024 | COT - HCBU - Building Progress | Partial Pass | Level #10 room close-out inspections; not ready: elevators not working. Will reschedule for 11 July. Electric underground at Northeast area for bollards - 2 conduits at 1”. Ok to cover progress areas. | |
07/11/2024 | COT - HCBU - Building Progress | Partial Pass | Level #10. room close-out inspections #1001 - 1032. | |
07/15/2024 | COT - HCBU - Building Progress | Partial Pass | Level #12, room units 1201 - 1223; close-out inspections. | |
07/16/2024 | COT - HCBU - Building Progress | Passed | ||
07/27/2023 | COT - HCBU - Building Progress | Partial Pass | Rebar at Level 10; stairwell B from Levels 10 to level 11. Columns on Level #10 at GL: 6.6/J, 7/J, 8/J, 8.5/J, K/6.5, K/7, M/6.6, 7/M, 6.8/M.3, 7.5/N, 7.5/H, 8/M. Masonry,pre-grout at GL: N/14 - 15, Elevator shaft C, North trash chute walls. Level #3, at stairwell D (3 planters). Amenity area at GL: R/14 - 17. Ok to place grout in progress areas. | |
07/31/2023 | COT - HCBU - Building Progress | Partial Pass | Level #5, Batch A, exterior framing and sheath nailing. Ok to cover exterior walls and waterproofing. | |
08/03/2023 | COT - HCBU - Building Progress | Partial Pass | Level #10, columns at GL: C/1, C/2, C/3 A/4, A/3, B/, B/2/ B/3, B/4. OK to set forms and place concrete in progress areas. | |
08/04/2023 | COT - HCBU - Building Progress | Partial Pass | Level #11 shear wall at stairwell A. Columns on Level #11 at GL: F.8/1, G/2, G.6/2.4, E.6/3, G/3, F/3, C/4. OK to set forms and place concrete. Level #11, Post tension cable system at Slab 11, pour #2, Ok to place concrete in progress areas. | |
08/08/2023 | COT - HCBU - Building Progress | Partial Pass | Level #11; Shear wall #5, Ok to set forms and place concrete. Columns at GL: C/8, B/8, B/7, C/6, C/7, B/6, A/6. OK to set forms and place concrete in progress areas. | |
08/09/2023 | COT - HCBU - Building Progress | Partial Pass | Level #11, post tension slab #3. Ok to place concrete in progress,areas. | |
08/11/2023 | COT - HCBU - Building Progress | Partial Pass | Level #11: stairwell/shear wall #D. OK to place forms and place concrete in progress areas. | |
08/17/2023 | COT - HCBU - Building Progress | Partial Pass | Level #12, placement #1: post tension cable system. Ok to place concrete in progress areas. | |
08/21/2023 | COT - HCBU - Building Progress | Partial Pass | Level 12, placement #1: columns at GL: A/1, A/2, B/1, B/2, A/3, A/4, B/3, C/4, C/3. OK to set forms and place concrete. Sheetrock nailing at Level #3, rooms 302, 305, 306, 307, 308,,309, 311. Ok to tape and texture progress areas. |
|
08/23/2023 | COT - HCBU - Building Progress | Partial Pass | Level #12: columns at GL:1/F.8, 2.4/G.6, 3/G, 3/G.6, 4/G.6, 5/G, 5/G.6, 4/F, 5.5/E. Ok to set forms and place concrete. Slab at level #12, placement #2. Ok to place,concrete in progress areas. | |
08/28/2023 | COT - HCBU - Building Progress | Partial Pass | Post tension cable system on Level #12, placement # 3. Ok to place concrete in progress area. | |
08/31/2023 | COT - HCBU - Building Progress | Not Ready | Contractor cancelled. Will reschedule for 1 September. | |
09/05/2023 | COT - HCBU - Building Progress | Partial Pass | Plumbing gas pressure test for Levels #1 to Level #9. Ok at 100 psi. | |
09/07/2023 | COT - HCBU - Building Progress | Partial Pass | Level #13, placement #2: Post tension cable system. Ok to place concrete in progress areas. | |
09/11/2023 | COT - HCBU - Building Progress | Partial Pass | Level #13, placement #2 vertical columns: F/6, F/7., F/8, F/8.5, G/6, G/6.6, G/7, G/8, G/8.5, H/6.6, H/7, H/8, H/8.5, B.1/8, C/8, A/7, B/7, C/7, A/6, B/6, C/6. Shear wall #5 at GL: 14 - 15. Ok to set forms and place concrete. | |
09/13/2023 | COT - HCBU - Building Progress | Partial Pass | Level #13, placement #3. Ok to place concrete in progress areas. | |
09/20/2023 | COT - HCBU - Building Progress | Partial Pass | Post tension cable system at Level #14, placement #2. Ok to place concrete in progress areas. Masonry pre-grout at Stairwell D at street side front, first lift at 0” - 48”. Ok to place grout in progress areas. | |
09/21/2023 | COT - HCBU - Building Progress | Partial Pass | Sheet rock nailing on Level #4; rooms 422, 421, 420, 419, 418, 417, 42#, 426, 425. Ok to tape progress areas. | |
10/02/2023 | COT - HCBU - Building Progress | Partial Pass | Masonry pre-grout at Stairwell D, (4th Avenue side) at 24’8” - 29’4”. Ok to grout progress areas. Sheetrock nailing on Level #5, rooms 505, 506, 507, 508, 509, 510, 511, 512. Ok to tape progress areas. | |
10/03/2023 | COT - HCBU - Building Progress | Partial Pass | Level #5, Mechanical, Electrical, and Plumbing in rooms 523, 525, 526, 527, 528, 529. | |
10/06/2023 | COT - HCBU - Building Progress | Partial Pass | Level #3 North and South Electric rooms, IDF room North. Level #4, North and South Electric rooms. | |
10/11/2023 | COT - HCBU - Building Progress | Partial Pass | 10/11/23: Domestic Water level 7 Area A under test ok to proceed. | |
10/16/2023 | COT - HCBU - Building Progress | Partial Pass | Level #6, Batch B Mechanical, Electrical, Plumbing intermediates in rooms:612, 613, 614, 615, 616, 617, 618, 619, 620, 621, 622. | |
10/19/2023 | COT - HCBU - Building Progress | Partial Pass | Level #6, Area A Sheetrock nailing in rooms 601, 602, 604. Ok to tape progress areas. | |
10/23/2023 | COT - HCBU - Building Progress | Partial Pass | Mechanical, Electrical, and Plumbing above ceiling for,units 625, 626, 627, 628, 629, 630, 631, 632. Hard lid ceiling areas on Level #4, Areas A, B, C. | |
10/30/2023 | COT - HCBU - Building Progress | Partial Pass | Level #7, Area A Mechanical, Electrical, Plumbing in rooms 701, 702, 703, 704, 705, 706, 707, 710, 711. | |
11/01/2023 | COT - HCBU - Building Progress | Partial Pass | 10/11/23: Domestic Water level 7 Area A under test ok to proceed. 11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed. |
|
11/28/2023 | COT - HCBU - Building Progress | Partial Pass | Level #8, Area “B”; Room units 812, 813, 814, 815, 816, 818, 819, 820, 821, 822. Electric rooms 841, 844. Ok to cover walls,in progress areas. | |
12/07/2023 | COT - HCBU - Building Progress | Partial Pass | Level #6; corridors above ceilings. Level #4, room #443 Lounge MEP, Level #6, room #643 lounge MEP, level #7, room #743 ME- | |
12/18/2023 | COT - HCBU - Building Progress | Partial Pass | Level #9, Area B; Units 911, 912, 913, 914, 915, 916, 917, 918, 919, 920 Mechanical, Plumbing, Electric. | |
12/26/2023 | COT - HCBU - Building Progress | Not Ready | Contractor cancelled, will reschedule for 27 December 2023. |