Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM02219

Parcel: 11706077R


Addresses:

211 N 4TH AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Permit Number - T22CM02219

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/04/2024 COT - HCBU - Building Progress Partial Pass Mechanical, electrical, and Plumbing for units 1001 - 1011 on Level #10, Area A. Ok to Sheetrock walls.
01/10/2024 COT - HCBU - Building Progress Partial Pass Electric intermediate in Electric rooms: 1041, 1044, 1141, 1144. Ok to cover walls,in progress areas.
01/16/2024 COT - HCBU - Building Progress Not Ready Contractor cancelled, will reschedule for 17 January
01/22/2024 COT - HCBU - Building Progress Partial Pass Level #13, Electric rooms at 1341 and 1344. Level #10 Mechanical, Electrical, Plumbing in units 1028, 1030, 1031, 1032. Ok to cover walls.
01/24/2024 COT - HCBU - Building Progress Not Ready Contractor cancelled, will reschedule for 25 January
01/29/2024 COT - HCBU - Building Progress Partial Pass Level #11, Area A: MEP for units 1101, 1102, 1103, 1104, 1105, 1106, 1!07, 1108, 1109, 1110, 1111. OK to cover interior walls.
01/31/2024 COT - HCBU - Building Progress Partial Pass Level #9, corridors above ceiling: Mechanical, electrical, plumbing. Ok to install ceiling grid in progress areas.
02/05/2024 COT - HCBU - Building Progress Partial Pass Level #11, Areas A & B; Mechanical, Electrical, Plumbing in units: 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121, 1122, 1123. Ok to insulate and cover walls and ceilings.
02/14/2024 COT - HCBU - Building Progress Partial Pass Level #11, Area A Sheetrock nailing in units 11-5, 1106, 1107, 1110, 1111. Ok to tape progress areas. Level #5 Fire caulking at columns in units 501 - 507. Units need to be rechecked to ensure proper caulking.
02/20/2024 COT - HCBU - Building Progress Partial Pass Level #12; MEP in units, 1202, 1203, 1214, 1215, 1216, 1217, 1218, 1219, 1220 1221. Units 1222 and 1223 were not,ready for inspection. NOTE: Level #10 above ceiling is,not ready for inspection due to numerous corrections needed.
02/26/2024 COT - HCBU - Building Progress Not Ready Contractor cancelled, will reschedule for 27 February.
03/01/2024 COT - HCBU - Building Progress Partial Pass Level #1, amenities area, offices, bike room above ceiling. Level #3, amenities areas, offices, gym area above ceiling.
03/05/2024 COT - HCBU - Building Progress Not Ready Elevator fronts framing are not ready. Fire caulking is incorrect.
03/06/2024 COT - HCBU - Building Progress Partial Pass Level #13, MEP in unit #1321. Sheetrock nailing in units : 1301, 1302, 1303, 1304, 1305, 1306, 1307, 1308, 1309, 1311. Ok to tape progress areas. Elevator face framing Fire caulking at levels #1 - #8.
03/07/2024 COT - HCBU - Building Progress Canceled Contractor cancelled, will reschedule for 8 March.
03/08/2024 COT - HCBU - Building Progress Partial Pass Elevator fronts, Fire caulking on levels 9 - 13 and level #1.
03/13/2024 COT - HCBU - Building Progress Partial Pass Trash chutes with fire sprinkler heads and supply water lines in trash rooms on levels 13, 11, 9, 7, 5, 3.
03/14/2024 COT - HCBU - Building Progress Partial Pass Level #13 sheet rock nailing in units: 1313, 1314, 1315, 1316, 1317, 1318, 1319. Ok to tape progress areas.
03/15/2023 COT - HCBU - Building Progress Partial Pass Inspection is for masonry pre-grout at GL: 8/J - N.7 at 0” - 48” AFFE. Ok to place grout in progress areas. Excavation/layout rebar: Slab L3P2 ; 20 columns have been dropped. Ok to set,forms and place concrete in progress areas.
03/15/2024 COT - HCBU - Building Progress Canceled Contractor cancelled inspection, will reschedule for 18 March.
03/18/2024 COT - HCBU - Building Progress Canceled Contractor cancelled. Will reschedule for 19 March.
03/19/2024 COT - HCBU - Building Progress Not Ready Level #11, corridor above ceiling trades; not ready as per Jason. Will reschedule.
03/20/2024 COT - HCBU - Building Progress Partial Pass Level #13, Sheetrock nailing in units 1318, 1319, 1320, 1321, 1322, 1323. Ok to tape progress areas. Level #11 over head MEP in corridors.
03/21/2024 COT - HCBU - Building Progress Canceled Contractor cancelled, will reschedule for 25 March.
03/25/2024 COT - HCBU - Building Progress Partial Pass 10/11/23: Domestic Water level 7 Area A under test ok to proceed.
11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed.
3/25/24: no inspection needed
03/26/2024 COT - HCBU - Building Progress Partial Pass Sheet rock nailing in unit #1322; two hour fire covering for interior steel beam
03/27/2024 COT - HCBU - Building Progress Partial Pass Level #3 corridors above ceiling. Ensure All penetrations are properly Fire caulked.
03/28/2024 COT - HCBU - Building Progress Partial Pass Level #12, corridors above ceiling. Ensure all penetrations are properly Fire caulked.
04/01/2024 COT - HCBU - Building Progress Canceled Contractor cancelled, will reschedule for 2 April
04/02/2024 COT - HCBU - Building Progress Canceled Contractor cancelled inspection.
04/03/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
04/04/2024 COT - HCBU - Building Progress Partial Pass Stairwell “C”, interior framing. Ok to insulate and sheet rock walls.
04/05/2024 COT - HCBU - Building Progress Partial Pass Information only; in-fill,in buck-hoist area.
04/08/2024 COT - HCBU - Building Progress Partial Pass Level #13, Mechanical, Plumbing, Electric above ceiling.
04/09/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
04/16/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
04/17/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
04/18/2024 COT - HCBU - Building Progress Partial Pass Information only; in- fill framing in buck hoist area (scheduling).
04/19/2024 COT - HCBU - Building Progress Partial Pass Requested location,for emergency generator disconnect. Disconnect to be located on column at left side of generator.
04/22/2024 COT - HCBU - Building Progress Canceled Contractor canceled
04/23/2024 COT - HCBU - Building Progress Partial Pass Exterior sheathing at in fill units (buck hoist areas) at Levels 3 - 13. Ok to waterproof progress areas.
04/24/2024 COT - HCBU - Building Progress Partial Pass Levels #12 and #13, above ceilings in,corridors. Ok to set ceiling grid and Sheetrock. Unit rooms 324, 424, 524, electric and plumbing. Mechanical to be installed.
04/26/2024 COT - HCBU - Building Progress Canceled Contractor cancelled: units not ready on levels 9 - 13. Will reschedule for 29 April
04/30/2024 COT - HCBU - Building Progress Partial Pass Framing, plumbing, and electric in units 1324, 1224, 1124, 1024, 924. Domestic water lines in units 1324, 1224, 1124, 1024, 924, 824, 727, 624, 524.
05/05/2023 COT - HCBU - Building Progress Partial Pass Level #5; pour #3 of Post Tension Cable system. Ok to place concrete in progress areas. Columns on Level #5: GL: H/8.5, G/8.5, F/8.5. Ok to set forms and place concrete in progress areas.
05/06/2024 COT - HCBU - Building Progress Partial Pass Fire caulking at elevators on Levels 8, 11, 12, 13. Ok to insulate and Sheetrock. Sheet rock nailing in units 824, 924. Ok to tape progress areas.
05/07/2024 COT - HCBU - Building Progress Partial Pass Sheet rock nailing in rooms 1024, 1124, 1224, 1324. Ok to tape progress areas.
05/08/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
05/11/2023 COT - HCBU - Building Progress Partial Pass Level #5: columns at GL: 11/L, 12/L, 13/L, 11/M, 12/M, 13/M, 11/N, 12/Q, 13/N, 11/N7, 11P, 13/P; 11/Q. OK to set forms and place concrete in progress areas. Masonry pre-grout at GL: 14/M - R, Southeast garage area at ramp, 9.5, CMU Wall at N/8 - 10 at 48”. Ok to place grout in progress areas.
05/13/2024 COT - HCBU - Building Progress Partial Pass Elevator lobby areas above ceilings at Levels #3 through Level 13.
05/15/2024 COT - HCBU - Building Progress Canceled
05/16/2023 COT - HCBU - Building Progress Partial Pass Excavation layout and rebar: Level #6, stair C. Columns at GL: B/1, A/1, A/2, A/3, A/4, B/2, B/3, B/4. Masonry pre-grout at corner Northwest at B/2. Crash wall at N/7 - 10.3. Ok to place grout in progress areas.
05/16/2024 COT - HCBU - Building Progress Partial Pass Stairwell “C” sheet rock nailing at Levels #1 - #10. West side of stairwell, walls have been Fire caulked and taped.
05/18/2023 COT - HCBU - Building Progress Partial Pass Level #6 slab; pour #3 at 6 -3. Columns on GL: 3/G, 4/G, G.6/2.4, 3/G.6, 4/G.6, 4/G, 5/G.6, 5/G, 6/G, 6/F. OK to set forms and place concrete.
05/21/2024 COT - HCBU - Building Progress Partial Pass Stairwell “C” Levels 3 - 13, Sheetrock and Fire caulking . Air pressure duct system 3 - 13.
05/22/2024 COT - HCBU - Building Progress Partial Pass Plumbing intermediate at gas line (2”) from Level #10 to roof. Pressure tested. Branch line (1”) to amenities area.
05/23/2023 COT - HCBU - Building Progress Partial Pass Level #6 columns at GL: F/8.5, G/8.5, H/8.5, J/8.5, G/6.6, H/6.6, J/6.6. Ok to set forms and place concrete.
05/28/2024 COT - HCBU - Building Progress Partial Pass 10/11/23: Domestic Water level 7 Area A under test ok to proceed.
11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed.
3/25/24: no inspection needed
5/28/24: no inspection needed.
05/30/2024 COT - HCBU - Building Progress Partial Pass Sheetrock nailing at elevator lobby’s on Levels 3 - 8. Ok to tape progress areas. Framing: Stairwell “C”, framing for positive air duct system on Levels 3 - 10. Ok to,sheet rock progress areas.
06/03/2024 COT - HCBU - Building Progress Partial Pass Stairwell “C” Sheetrock nailing at,levels #5 - 13.
06/05/2024 COT - HCBU - Building Progress Canceled Contractor cancelled; will reschedule.
06/10/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
06/11/2024 COT - HCBU - Building Progress Canceled Contractor cancelled.
06/26/2024 COT - HCBU - Building Progress Partial Pass Level #4, Room units 401 - 420 close - out inspections. Required corrections submitted to GC.
06/27/2024 COT - HCBU - Building Progress Partial Pass Close out room inspections on Level #4: 421, 422, 423, 424, 425, 426, 427, 428, 429, 430, 431, 432. Room unit inspections on Level #5: 524, 525, 526, 527, 528, 529, 530
06/28/2024 COT - HCBU - Building Progress Partial Pass Close - out room inspections at Level #5, Room units: 501 - 523.
07/02/2024 COT - HCBU - Building Progress Partial Pass Close out unit inspections at Level 6; 601 - 619, Level 7; 701 -712.
07/03/2024 COT - HCBU - Building Progress Partial Pass Level #7, close out unit inspections at 712 - 732.
07/08/2024 COT - HCBU - Building Progress Partial Pass Level #8; room units close-out inspection #801 - 832.
07/09/2024 COT - HCBU - Building Progress Partial Pass Close-out room inspections at Level #9: #901 - 932. Excavation rebar: 9 light pole caisson footings, ufers are in place. Ok to place cages and concrete in progress areas.
07/10/2024 COT - HCBU - Building Progress Partial Pass Level #10 room close-out inspections; not ready: elevators not working. Will reschedule for 11 July. Electric underground at Northeast area for bollards - 2 conduits at 1”. Ok to cover progress areas.
07/11/2024 COT - HCBU - Building Progress Partial Pass Level #10. room close-out inspections #1001 - 1032.
07/15/2024 COT - HCBU - Building Progress Partial Pass Level #12, room units 1201 - 1223; close-out inspections.
07/16/2024 COT - HCBU - Building Progress Passed
07/27/2023 COT - HCBU - Building Progress Partial Pass Rebar at Level 10; stairwell B from Levels 10 to level 11. Columns on Level #10 at GL: 6.6/J, 7/J, 8/J, 8.5/J, K/6.5, K/7, M/6.6, 7/M, 6.8/M.3, 7.5/N, 7.5/H, 8/M. Masonry,pre-grout at GL: N/14 - 15, Elevator shaft C, North trash chute walls. Level #3, at stairwell D (3 planters). Amenity area at GL: R/14 - 17. Ok to place grout in progress areas.
07/31/2023 COT - HCBU - Building Progress Partial Pass Level #5, Batch A, exterior framing and sheath nailing. Ok to cover exterior walls and waterproofing.
08/03/2023 COT - HCBU - Building Progress Partial Pass Level #10, columns at GL: C/1, C/2, C/3 A/4, A/3, B/, B/2/ B/3, B/4. OK to set forms and place concrete in progress areas.
08/04/2023 COT - HCBU - Building Progress Partial Pass Level #11 shear wall at stairwell A. Columns on Level #11 at GL: F.8/1, G/2, G.6/2.4, E.6/3, G/3, F/3, C/4. OK to set forms and place concrete. Level #11, Post tension cable system at Slab 11, pour #2, Ok to place concrete in progress areas.
08/08/2023 COT - HCBU - Building Progress Partial Pass Level #11; Shear wall #5, Ok to set forms and place concrete. Columns at GL: C/8, B/8, B/7, C/6, C/7, B/6, A/6. OK to set forms and place concrete in progress areas.
08/09/2023 COT - HCBU - Building Progress Partial Pass Level #11, post tension slab #3. Ok to place concrete in progress,areas.
08/11/2023 COT - HCBU - Building Progress Partial Pass Level #11: stairwell/shear wall #D. OK to place forms and place concrete in progress areas.
08/17/2023 COT - HCBU - Building Progress Partial Pass Level #12, placement #1: post tension cable system. Ok to place concrete in progress areas.
08/21/2023 COT - HCBU - Building Progress Partial Pass Level 12, placement #1: columns at GL: A/1, A/2, B/1, B/2, A/3, A/4, B/3, C/4, C/3. OK to set forms and place concrete.
Sheetrock nailing at Level #3, rooms 302, 305, 306, 307, 308,,309, 311. Ok to tape and texture progress areas.
08/23/2023 COT - HCBU - Building Progress Partial Pass Level #12: columns at GL:1/F.8, 2.4/G.6, 3/G, 3/G.6, 4/G.6, 5/G, 5/G.6, 4/F, 5.5/E. Ok to set forms and place concrete. Slab at level #12, placement #2. Ok to place,concrete in progress areas.
08/28/2023 COT - HCBU - Building Progress Partial Pass Post tension cable system on Level #12, placement # 3. Ok to place concrete in progress area.
08/31/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled. Will reschedule for 1 September.
09/05/2023 COT - HCBU - Building Progress Partial Pass Plumbing gas pressure test for Levels #1 to Level #9. Ok at 100 psi.
09/07/2023 COT - HCBU - Building Progress Partial Pass Level #13, placement #2: Post tension cable system. Ok to place concrete in progress areas.
09/11/2023 COT - HCBU - Building Progress Partial Pass Level #13, placement #2 vertical columns: F/6, F/7., F/8, F/8.5, G/6, G/6.6, G/7, G/8, G/8.5, H/6.6, H/7, H/8, H/8.5, B.1/8, C/8, A/7, B/7, C/7, A/6, B/6, C/6. Shear wall #5 at GL: 14 - 15. Ok to set forms and place concrete.
09/13/2023 COT - HCBU - Building Progress Partial Pass Level #13, placement #3. Ok to place concrete in progress areas.
09/20/2023 COT - HCBU - Building Progress Partial Pass Post tension cable system at Level #14, placement #2. Ok to place concrete in progress areas. Masonry pre-grout at Stairwell D at street side front, first lift at 0” - 48”. Ok to place grout in progress areas.
09/21/2023 COT - HCBU - Building Progress Partial Pass Sheet rock nailing on Level #4; rooms 422, 421, 420, 419, 418, 417, 42#, 426, 425. Ok to tape progress areas.
10/02/2023 COT - HCBU - Building Progress Partial Pass Masonry pre-grout at Stairwell D, (4th Avenue side) at 24’8” - 29’4”. Ok to grout progress areas. Sheetrock nailing on Level #5, rooms 505, 506, 507, 508, 509, 510, 511, 512. Ok to tape progress areas.
10/03/2023 COT - HCBU - Building Progress Partial Pass Level #5, Mechanical, Electrical, and Plumbing in rooms 523, 525, 526, 527, 528, 529.
10/06/2023 COT - HCBU - Building Progress Partial Pass Level #3 North and South Electric rooms, IDF room North. Level #4, North and South Electric rooms.
10/11/2023 COT - HCBU - Building Progress Partial Pass 10/11/23: Domestic Water level 7 Area A under test ok to proceed.
10/16/2023 COT - HCBU - Building Progress Partial Pass Level #6, Batch B Mechanical, Electrical, Plumbing intermediates in rooms:612, 613, 614, 615, 616, 617, 618, 619, 620, 621, 622.
10/19/2023 COT - HCBU - Building Progress Partial Pass Level #6, Area A Sheetrock nailing in rooms 601, 602, 604. Ok to tape progress areas.
10/23/2023 COT - HCBU - Building Progress Partial Pass Mechanical, Electrical, and Plumbing above ceiling for,units 625, 626, 627, 628, 629, 630, 631, 632. Hard lid ceiling areas on Level #4, Areas A, B, C.
10/30/2023 COT - HCBU - Building Progress Partial Pass Level #7, Area A Mechanical, Electrical, Plumbing in rooms 701, 702, 703, 704, 705, 706, 707, 710, 711.
11/01/2023 COT - HCBU - Building Progress Partial Pass 10/11/23: Domestic Water level 7 Area A under test ok to proceed.
11/1/23: Level 4 hard lid framing per plan ok to proceed, fire dampers installed, all penetrations in level 4 corridor fire caulked and sealed.
11/28/2023 COT - HCBU - Building Progress Partial Pass Level #8, Area “B”; Room units 812, 813, 814, 815, 816, 818, 819, 820, 821, 822. Electric rooms 841, 844. Ok to cover walls,in progress areas.
12/07/2023 COT - HCBU - Building Progress Partial Pass Level #6; corridors above ceilings. Level #4, room #443 Lounge MEP, Level #6, room #643 lounge MEP, level #7, room #743 ME-
12/18/2023 COT - HCBU - Building Progress Partial Pass Level #9, Area B; Units 911, 912, 913, 914, 915, 916, 917, 918, 919, 920 Mechanical, Plumbing, Electric.
12/26/2023 COT - HCBU - Building Progress Not Ready Contractor cancelled, will reschedule for 27 December 2023.