| 01/05/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Sheetrock nailing on Level #9, units: 912, 913, 914, 915, 916, 917, 918, 919, 921. Building above ceiling at Level #7 corridors. |
| 01/12/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #4, Fire Caulking at columns in units: 430, 428, 426, 427, 425, 421, 429, 450, 422, 418, 417, 408, 409, 407. |
| 01/17/2024 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled, will reschedule for 18 January |
| 01/18/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #10. Area C, Mechanical, Electrical, Plumbing in units 1023, 1025, 1026, 1027, 1027 (except for kitchen duct system) |
| 01/23/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Sheetrock nailing on Level #10, Area B; units 1013, 1014, 1016. Ok to tape progress areas. Level #8 corridor ceilings for Mechanical, Electrical, Plumbing. Ok to cover,progress areas. |
| 01/26/2024 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled. |
| 01/30/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #10, sheet rock nailing in units 1020, 1021, 1022, 1023. Ok to tape progress areas. |
| 02/06/2024 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled. Will reschedule. |
| 02/13/2024 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled, will reschedule for 14 February |
| 02/15/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #11 sheet rock nailing in units 1113, 1114, 1115, 1116, 1117, 1118, 1119. Ok to tape progress areas. |
| 02/21/2024 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled, will reschedule for 22 February |
| 03/11/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #3, amenities area Sheetrock interior walls; all areas except for restrooms and sauna rooms. |
| 03/12/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Trash chutes frontal area Fire caulking at Levels 3 - 12. |
| 03/13/2024 |
COT - HCBU - Interior Shear Bracing |
|
Canceled |
Contractor cancelled. |
| 03/19/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #2 North storage room, MEP. Is there a requirement for an electric outlet in this room? |
| 05/31/2024 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Sheet rock nailing in Elevator lobby’s at levels 1 - 2, 9 -13. Ok to tape in progress areas. |
| 07/15/2024 |
COT - HCBU - Interior Shear Bracing |
|
Passed |
|
| 10/11/2023 |
COT - HCBU - Interior Shear Bracing |
|
Re-inspection required |
10/11/23: Level 5 rooms 517-522 requires re-inspection. Screws must be 3/8" from edge of drywall. Nailing schedule not followed (large spans of missing screws). |
| 12/01/2023 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Sheetrock nailing on Level #7; Electric rooms and storage rooms at 746, 745, 744, 741, 740. Level #6 Electric rooms and storage rooms at 640, 641, 644, 647. Ok to tape progress areas. |
| 12/15/2023 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #8, sheet rock nailing in units 818, 819, 820, 821, 823, 827. Ok to tape throughout progress areas. |
| 12/22/2023 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
Contractor cancelled due to weather conditions, will reschedule for 26 December |
| 12/29/2023 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #9, Area A, Sheetrock nailing in units : 901, 902, 903, 904, 905, 906, 907, 908, 909. Ok to tape progress areas. MEP in unit #923. |