Permit: T22CM02219

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled. Will reschedule for 23 January.
01/31/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Post tension cable system for level #2, slab #2. Ok to place concrete in progress areas.
02/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Colorado section, slab at 12- 16/K - R. Columns at CC4 at 4.5/F, CC1F at 4.5/E, CC1G at 5.5, CC4 C at 5.5/F, CC4H at 4/G, CC7 at 1/F.8, CC2G at 2.4/G.7. Ok to place concrete in progress areas.
02/06/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Level #2, Shear wall #5 at GL: 6 -7/D -E. Columns on Level #2: CC1R at 8.5/H, CC4F at 8/F, CC1E at 8/C, CC1E at 8/C, CC4R at 8.5/H, CC4A at 7/C, CC1 at 6/A, CC1B at 6/B. OK to place concrete in progress areas.
02/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass MEP on Level #12 in units 1222 and d 1223. Level #10 areas #A & B above ceiling for MEP inspection. Level #1 Amenities area for MEP in walls.
04/19/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Level 4 -5, columns at GL: H/7, H/8, H/8.5, H/6.6, G/8.5, G/8, F/8.5, F/8, F/7, C/7, C/8, B/7. OK to set forms and place concrete. Post tension cable system on Level #4, pour #3. Ok to place concrete in progress areas. Level #4, shear wall #5, Ok to set forms and place concrete in progress areas.
07/15/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed
10/24/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
10/31/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
11/08/2022 COT - HCBU - Excavation/Rebar/Zoning  Canceled
11/10/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall footing WF22-03 at GL: A - B.5/1 - 2.3; column footing CF26-6 at GL: A - B.5/2.8 - 4.4; WF 8-6; CF8-0A; WF 8-6; WF3. Ok to place concrete in progress areas.
11/14/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns: CC1 at GL: 8.5/G; CC1 at GL: N/8.5; G.6/4 - 4.4; wall footings at GL; F.5 - B.8/3.5 - 5.8; 5 - 6; retaining wall at GL; G.7/3 -4.4. Column footings: CF12-0C; CF12-6A; CF5-0A; CF12-6A. OK to place concrete in progress areas.
11/15/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Mat #02: at GL: 5.8 - 7.4/F.4 - B.8 (columns CC4 & CC1. Shear wall #SW12, Perimeter wall at GL: G.6/4.4 - 5 ; L.4/7 - 8; A/2 - 5.5. OK to place concrete in progress areas.
11/16/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Exterior wall at GL: AA/G.E - G.6. #5 bars both horizontal and vertical at 18” O.C. Column CC6 at GL: F/3. OK to place concrete in progress areas
11/17/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Mat #05, at GL: G.5/11 - 12(24’ x 40’ x 5’ 6”); shear wall at GL: 13.2/2; columns CF23, CF24 (2), CF5 at GL: C/3, CF22, CC5 at C/3, CC28 at E/3, CC17 at L.5/8, CF9-OA; wall footings at 2.0, CC16 at M/8, L.3 - M/8, M/8-8.5. Ok to place concrete in progress areas.
11/18/2022 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass