| 10/26/2022 |
COT - LCEL - Electrical Progress |
|
Not Ready |
|
| 01/04/2023 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Ten each 3” electrical conduits at GL: L.5/7 -8, 7-8/M -M.3, 10/M-M.3. Ok to cover progress areas. |
| 04/18/2024 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Meter sets for levels #11, 12, 13 (72 requests total). Forwarded to DPDS to be forwarded to TEP for esters. |
| 04/19/2024 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Meter sets for Levels 8, 9, 10. 72 meter sets forwarded to DPDS for forwarding to TEP. |
| 05/06/2024 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Meter sets (147) on Levels 4, 6, 7 8 |
| 07/15/2024 |
COT - LCEL - Electrical Progress |
|
Passed |
|
| 10/04/2023 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Level #5, Batch C Mechanical, Electrical, Plumbing in rooms 530, 531, 532. Ok to Sheetrock progress areas. |
| 12/16/2022 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Conduits for car charging stations (4) at North and South sides of basement level of parking garage. Ok to cover progress areas. |
| 12/21/2022 |
COT - LCEL - Electrical Progress |
|
Canceled |