Permit: T22CM02219

Parcel: 11706077R


Addresses:

211 N 4TH AV

Inspection Status: Not Ready

Inspection History: COT - LCEL - Electrical Progress  

Date Description Inspector Results Comments
10/26/2022 COT - LCEL - Electrical Progress   Not Ready
01/04/2023 COT - LCEL - Electrical Progress   Partial Pass Ten each 3” electrical conduits at GL: L.5/7 -8, 7-8/M -M.3, 10/M-M.3. Ok to cover progress areas.
04/18/2024 COT - LCEL - Electrical Progress   Partial Pass Meter sets for levels #11, 12, 13 (72 requests total). Forwarded to DPDS to be forwarded to TEP for esters.
04/19/2024 COT - LCEL - Electrical Progress   Partial Pass Meter sets for Levels 8, 9, 10. 72 meter sets forwarded to DPDS for forwarding to TEP.
05/06/2024 COT - LCEL - Electrical Progress   Partial Pass Meter sets (147) on Levels 4, 6, 7 8
07/15/2024 COT - LCEL - Electrical Progress   Passed
10/04/2023 COT - LCEL - Electrical Progress   Partial Pass Level #5, Batch C Mechanical, Electrical, Plumbing in rooms 530, 531, 532. Ok to Sheetrock progress areas.
12/16/2022 COT - LCEL - Electrical Progress   Partial Pass Conduits for car charging stations (4) at North and South sides of basement level of parking garage. Ok to cover progress areas.
12/21/2022 COT - LCEL - Electrical Progress   Canceled Contractor cancelled.