Permit: T21CM08080

Parcel: 132131250


Addresses:

3456 S KINO PW

Inspection Status: Not Ready

Inspection History: COT - LCPL - Rough Soil 

Date Description Inspector Results Comments
10/26/2022 COT - LCPL - Rough Soil  Not Ready
10/03/2022 COT - LCPL - Rough Soil  JBURGE Partial Approval Entered by VVERA1 - Partial. Domestic water line (2”), from water main line to building; approximately 150’. Ok to cover progress areas.
09/08/2022 COT - LCPL - Rough Soil  WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval building 8 for grease interceptor and associated waste lines, ok to cover
08/03/2022 COT - LCPL - Rough Soil  DMUNIZ Partial Approval Entered by VVERA1 - partial, main Sanitary and Grease lines installed under foundation installed and tested.
02/16/2023 COT - LCPL - Rough Soil  Partial Pass approval for shel only
03/02/2023 COT - LCPL - Rough Soil  Passed shell only