Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T19CM05218

Parcel: 12404098A


Addresses:

947 N PARK AV

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
08/10/2021 MECHANICAL - INTERMEDIATE Approved 4090
06/11/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CONTRACTOR CANCELLED
06/10/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
06/09/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection
06/08/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
06/04/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
06/03/2021 MECHANICAL - INTERMEDIATE Cancelled CANCELLED BY CONTRACTOR
06/03/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
06/02/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
06/01/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Unit 809.
05/28/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/27/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CONTRACTOR CANCELLED
05/26/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/26/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
05/25/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
05/25/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/24/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/24/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Unit 806.
05/21/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
05/20/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/20/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/20/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
05/19/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection
05/19/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/18/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/18/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
05/17/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/17/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 18 May.
05/14/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/13/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Line Sets to roof Units.
05/12/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/12/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 12 May.
05/11/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/11/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Unit 811.
05/10/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/10/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
05/07/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 10 May
05/07/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/06/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/06/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 7 May
05/05/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/05/2021 MECHANICAL - INTERMEDIATE Cancelled Not ready. Contractor cancelled will reschedule for 6 May
05/04/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
05/04/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Units 807; 810
05/03/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Will reschedule for 4 May
05/03/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/30/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #7; Room Unit 709
04/30/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/29/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/28/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Units 805 and student lounge
04/27/2021 MECHANICAL - INTERMEDIATE Partial Approval PARTIAL ROOM UNIT 812
04/27/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/26/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/20/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 21 April
04/19/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 20 April
04/19/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/16/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/15/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CONTRACTOR CANCELLED
04/14/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Room Unit 801;
04/14/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/13/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/12/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 13 April.
04/09/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/09/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection . Not ready. Contractor cancelled will reschedule for 12 April.
04/08/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/08/2021 MECHANICAL - INTERMEDIATE Partial Approval PARTIAL LEVEL 4 ROOM UNIT 409
04/07/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/05/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
04/01/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/31/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Units 814; 819.
03/31/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/30/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/30/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level#8; Room Units 815; 818.
03/26/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/25/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Room Units 817; 309; 209
03/24/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/24/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room 816.
03/23/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
03/23/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/22/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/19/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Unit 804.
03/18/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #8; Room Units 802; 803.
03/18/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/17/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
03/02/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CONTRACTOR CANCELLED
03/01/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
02/04/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CONTRACTOR CANCELLED
02/03/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
02/03/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #7; Room Units 703; 704; 705; 706; 707.
02/02/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CANCELLED BY CONTRACTOR
02/02/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
02/01/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY CANCELLED BY CONTRACTOR
02/01/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
01/29/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
01/29/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #7; Room Units 701; 702; 704; 710.
01/28/2021 MECHANICAL - INTERMEDIATE Cancelled IVRS - AP canceled
01/27/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #7; Room Units 711; 712; 718.
01/26/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #7; Room Units 713 - 717.
01/22/2021 MECHANICAL - INTERMEDIATE Approved NOT READY CANCELLED BY CONTRACTOR
01/20/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #6; Room Units 604; 606
01/14/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection NOT READY, CONTRACTOR CANCELLED
01/12/2021 MECHANICAL - INTERMEDIATE Partial Approval PARTIAL LEVEL #6 ROOM UNITS 601, 610, 611, 612
01/11/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #6; Room Units 613; 614; 615; 616; 67; 618.
01/07/2021 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
01/06/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #5; Room Units 501; 502; 503; 505; 506; 507; 508
01/05/2021 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #4; Room Units 510; 511; 516; 517; 518
12/31/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
12/30/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #5; Room Units 510; 513; 514; 515
12/29/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
12/28/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
12/23/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
12/22/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #4; Room Units 401; 402; 403; 405; 406; 407; 410.
12/21/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 22 December.
12/18/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #4; Room Units 411; 418
12/17/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #4 Room Units 413; 414; 418
12/16/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #4; Room Units 415; 416; 417.
12/11/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
12/09/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #3; Room Units 304;305; 307.
12/08/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 9 December.
12/07/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #3; Room Units 302; 303; 308.
12/04/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Room Units. 206; 301; 310; 311; 312; 317.
12/03/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
12/02/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #3; Room Units 316; 318.
12/01/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level 3; Room Units 313; 314; 315. Ok to insulate and cover walls.
11/30/2020 MECHANICAL - INTERMEDIATE Cancelled Canceled by contractor.
11/27/2020 MECHANICAL - INTERMEDIATE Denied All denied. No contact.**
11/25/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection
11/24/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Units, 205, 207, 208, student lounge.
11/23/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #2 Room Units 201; 202; 204.
11/20/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
11/17/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #2; Room Units 210; 211; 212
11/16/2020 MECHANICAL - INTERMEDIATE Cancelled Not ready, contractor cancelled. Will reschedule for 17 November.
11/13/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #2; Room Units 213; 214; 215
11/06/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #1; Room Units 103; 104; 105.
11/04/2020 MECHANICAL - INTERMEDIATE Partial Approval Partial. Level #1; Room Units 101; 102.