Permit: T19CM05218

Parcel: 12404098A


Addresses:

947 N PARK AV

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
08/10/2021 BUILDING - PROGRESS Approved 1090
08/09/2021 BUILDING - PROGRESS Cancelled ca
Per contractor.
08/06/2021 BUILDING - PROGRESS Partial Approval Partial. Room Unit finals: 815; 816; 817; 818; 711; 609
08/05/2021 BUILDING - PROGRESS Cancelled Canceled by contractor
08/04/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled.
07/30/2021 BUILDING - PROGRESS Not ready for Inspection NOT READY CONTRACTOR CANCELLED
07/29/2021 BUILDING - PROGRESS Partial Approval Partial. Level #7; Room Units 702, 703, 704, 705, 706, 707, 708, 709, 710. Room inspection finals.
07/28/2021 BUILDING - PROGRESS Partial Approval Partial. Level #7; Room Units 712-718 final room inspections complete.
07/26/2021 BUILDING - PROGRESS Not ready for Inspection NOT READY CANCELLED BY CONTRACTOR
07/23/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Level #7; Room Units, bathrooms, GFI outlets not working properly.
07/22/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor canceled due to elevators not working. Will reschedule for 23 July.
07/21/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor canceled. Room units are not ready for inspection.
07/19/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Room units on Level #7 are not ready for inspection. Reschedule for 20 July.
07/16/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor canceled.
07/15/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled; South wing Room Units not ready for inspection. Will reschedule.
07/14/2021 BUILDING - PROGRESS Partial Approval Partial. Pre-TCO walk through with Armando and The Parker staff.
07/13/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Pre-Certificate of Occupancy walk through scheduled for 0800 hours; 14 July.
07/12/2021 BUILDING - PROGRESS Partial Approval Partial. Level #6 Room Units #601-616. Final Room inspections.
07/09/2021 BUILDING - PROGRESS Not ready for Inspection . Not ready. Contractor cancelled will reschedule for 12 July for Room Units on Level #8.
07/08/2021 BUILDING - PROGRESS Partial Approval Partial. Level #8; Room Unit #809: relocation of electric outlet in kitchen area.
07/07/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Level #6; Room Units not ready for inspection, will reschedule for 8 July.
07/02/2021 BUILDING - PROGRESS Not ready for Inspection Not ready; Room Units on Level #6 are not ready for inspection. Will reschedule for 6 July.
07/01/2021 BUILDING - PROGRESS Partial Approval Partial. Level #5; Room Unit Finals; #501 through #518; except for Room #509.
06/30/2021 BUILDING - PROGRESS Partial Approval Not ready. Level #5 Room Units inspections to be rescheduled for July.
06/18/2021 BUILDING - PROGRESS Partial Approval Partial. Level #4; Room Units final inspection for Units 401-418; except for Unit 409.
06/17/2021 BUILDING - PROGRESS Partial Approval Partial. Level #3; Room Unit 309; Final Room inspection. Information: inspection scheduling for Temporary Certificate of Occupancy.
06/16/2021 BUILDING - PROGRESS Partial Approval Partial. Level #3; Room Units 301-318; Room Finals for Electric, Plumbing; mechanical Finals.
06/15/2021 BUILDING - PROGRESS Partial Approval Partial. Room Units Finals on Level #2; Room Units #201-202; 204-218.