Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/27/2021 |
SHEET ROCK NAILING |
|
Approved |
|
| 04/30/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #1 Amenities area. Ok to tape progress. |
| 03/30/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Courtyard, South walls. Ok to scratch coat progress. |
| 03/18/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Levels 2 and 3; Corridor walls and ceilings. Ok to tape progress areas. |
| 03/17/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
. Not ready. Contractor cancelled. |
| 03/16/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2 shafts; sheet rocked and fire caulked. Ok to clean and cover shafts. |
| 03/11/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
NOT READY WILL RESCHEDULE FOR 12TH MARCH |
| 03/04/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 03/01/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #6; Room Units 601; 606; 617. Ok to tape progress areas. |
| 02/26/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
PARTIAL LEVEL #7 UNITS 701 THRU 718 |
| 02/25/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #6; Room Units 602; 603; 604; 605; 607; 610; 611. Ok to tape progress areas. |
| 02/23/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE FOR 24TH FEBRUARY |
| 02/22/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #6; Room Units 613; 614; 615; 616. Ok to tape progress areas |
| 02/18/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2; Return air shafts at East and South Corridors. Ensure all shafts are properly fire caulked. |
| 02/17/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2 Corridor walls and ceilings. Ok to tape progress areas. |
| 02/09/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #5; Room Units 501; 502; 503; 504; 505; 506; 507; 508; 510. Ok to tape progress areas. |
| 02/03/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 4 February. |
| 02/02/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 02/01/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
PARTIAL LEVEL #5 ROOM UNITS 512, 513,514 515, 516, OK TO TAPE PROGRESS |
| 01/22/2021 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 01/21/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
PARTIAL LEVEL #4, ROOM UNITES 408, 410, 412, 416, OK TO TAPE PROGRESS AREA |
| 01/20/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #4; Room Units 402 - 407. Ok to tape progress areas. |
| 01/07/2021 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #3 Room Units 304; 305; 306; Level #4 Room Units 415; 417. Ok to tape progress areas. |
| 12/30/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 12/29/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #3; Room Units 301; 311; 313; 314; 315; 316; 317; 318. Ok to tape progress areas. |
| 12/28/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 12/23/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2; Room Units 201; 202; 203; 204; 205; 206; 207; 208; 210; 211; 212; 217; 218. Ok to tape progress areas. |
| 12/17/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level#2; Room Units 201; 202; 204; 205; 208; 211; Lounge. Ok to tape progress areas. |
| 12/16/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2; Room Units 212; 216; 217; 218. Ok to tape progress areas. |
| 12/07/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Level #2; Room Units 213; 214; 215. Ok to tape progress areas. |
| 11/25/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Partial. Units 101 thru 105. |
| 10/30/2020 |
SHEET ROCK NAILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, will reschedule for 2 November. |