| 07/27/2021 |
FRAMING |
|
Approved |
|
| 06/11/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED |
| 06/09/2021 |
FRAMING |
|
Not ready for Inspection |
|
| 06/04/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/03/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE FOR 4 JUNE |
| 06/01/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8: Room Unit 809; Ok to insulate and cover walls. |
| 05/27/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 3 June. |
| 05/26/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled |
| 05/25/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, Level #8 incomplete. |
| 05/24/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Unit 806. Ok to insulate and cover walls |
| 05/21/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. Level #8 Room Units not ready. Will reschedule for 24 May. |
| 05/20/2021 |
FRAMING |
|
Partial Approval |
Partial. Room Units inspection scheduling for Level #8. |
| 05/19/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 05/18/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 05/17/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 18 May. |
| 05/13/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; HVAC Shafts, Fire caulked. |
| 05/12/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, will reschedule for 12 May. |
| 05/11/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Unit 811. Ok to insulate and cover walls. |
| 05/10/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled |
| 05/07/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 10 May |
| 05/06/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 7 May |
| 05/05/2021 |
FRAMING |
|
Cancelled |
Not ready. Contractor cancelled will reschedule for 6 May |
| 05/04/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Units 807; 810. Ok to insulate and cover walls. |
| 05/03/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Will reschedule for 4 May |
| 04/30/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Unit 709. Ok to insulate and cover walls. |
| 04/28/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Units 805; Student lounge. Ok to insulate and cover walls. |
| 04/27/2021 |
FRAMING |
|
Partial Approval |
Partial. Room Unit 812. Ok to insulate and cover walls. |
| 04/20/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 21 April |
| 04/19/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 20 April |
| 04/15/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED |
| 04/14/2021 |
FRAMING |
|
Partial Approval |
Partial. Room Unit 801; Ok to insulate and cover walls. |
| 04/12/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 13 April |
| 04/09/2021 |
FRAMING |
|
Not ready for Inspection |
. Not ready. Contractor cancelled will reschedule for 12 April. |
| 04/08/2021 |
FRAMING |
|
Partial Approval |
PARTIAL LEVEL 3 ROOM UNIT 409 |
| 03/31/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Units 814; 819. Ok to insulate and cover walls |
| 03/30/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Units 815; 818. Ok to insulate and cover walls. |
| 03/25/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Unit 817; Level #3; Room 309; Level #2; Room 209. Ok to insulate and cover walls. |
| 03/24/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room 816. Ok to insulate and cover walls. |
| 03/23/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 03/19/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Unit ; 804. Ok to insulate and cover walls. |
| 03/18/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #8; Room Units 802; 803: Ok to insulate and cover walls. |
| 03/02/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED |
| 02/04/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE 5 FEBRUARY |
| 02/03/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 703; 704; 705; 706; 707. Ok to insulate and cover walls. |
| 02/02/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE 3 FEBRUARY |
| 02/01/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 01/29/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 701; 702; 704; 710. Ok to insulate and cover walls. |
| 01/27/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 711; 712; 718. Ok to cover walls. |
| 01/26/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 713 - 717. Ok to insulate and cover walls. |
| 01/22/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY CONTRACTOR CANCELLED WILL RESCHEDULE FOR 25 JANUARY |
| 01/20/2021 |
FRAMING |
|
Partial Approval |
PARTIAL - Partial. Level #6; Room Units 604; 606. Ok to insulate and cover walls. |
| 01/14/2021 |
FRAMING |
|
Not ready for Inspection |
NOT READY, CONTRACTOR CANCELLED WILL RESCHEDULE FOR 15 JANUARY |
| 01/12/2021 |
FRAMING |
|
Partial Approval |
PARTIAL - LEVEL #6, ROOM UNITS 601, 610, 611, 612 OK TO INSULATE AND COVER WALLS |
| 01/11/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #6; Room Units 613; 614; 615;616; 617; 618. Ok to insulate and cover walls. |
| 01/07/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled |
| 01/06/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #5; Room Units 501; 502; 503; 505; 506; 507; 508. Ok to insulate and cover walls. |
| 01/05/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #5; Room Units 510; 511; 516; 517; 518. Ok to insulate and cover walls. |
| 12/31/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled |
| 12/30/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #5; Room Units 510; 513; 514; 515. Ok to insulate and cover walls. |
| 12/28/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 12/23/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 12/22/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #4; Room Units 401; 402; 403; 405; 406; 407; 410. Ok to cover walls. |
| 12/21/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, will reschedule for 22 December. |
| 12/18/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #4; Room Units 411; 418. Ok to insulate and cover walls. |
| 12/17/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #4 Room Units 413; 414; 418. Ok to insulate and cover walls. |
| 12/16/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #4; Room Units 415; 416; 417. Ok to insulate and cover walls at. |
| 12/11/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 12/09/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #3; Room Units 304; 305;307. Ok to insulate and cover walls. |
| 12/08/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, will reschedule for 9 December |
| 12/07/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #3; Room Units 302; 303; 308. Ok to insulate and cover walls |
| 12/04/2020 |
FRAMING |
|
Partial Approval |
Partial. Room Units 206; 301; 310; 311; 312; 317. Ok to insulate and cover walls. |
| 12/03/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 4 December. |
| 12/02/2020 |
FRAMING |
|
Partial Approval |
Partial. Roof Level; Elevator Room, restroom, stairwell B. Level #3; Room Units 316; 318. Ok to cover progress areas. |
| 12/01/2020 |
FRAMING |
|
Partial Approval |
Partial. Level 3; Room Units 313; 314; 315. |
| 11/30/2020 |
FRAMING |
|
Cancelled |
Canceled by contractor. |
| 11/27/2020 |
FRAMING |
|
Denied |
All denied. No contact.** |
| 11/25/2020 |
FRAMING |
|
Not ready for Inspection |
|
| 11/24/2020 |
FRAMING |
|
Partial Approval |
Partial. Units, 205, 207, 208, student lounge. |
| 11/23/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2 Room Units 201; 202; 204. Ok to cover walls and ceilings. |
| 11/20/2020 |
FRAMING |
|
Partial Approval |
Partial. Roof level Parapet walls Northeast and Northwest. Ok to cover progress areas. |
| 11/18/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2 Room Units, 204; 205; 206; 207; 208; 210; 211; 212. |
| 11/17/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2; Room Units 210; 211; 212. Ok to insulate and cover walls. |
| 11/16/2020 |
FRAMING |
|
Partial Approval |
Partial. Roof Level; Parapet walls; South and Southeast. Planter walls at East side of building. Garage level #1; West wall area: Duct Bank. Ok to set forms and place concrete. |
| 11/13/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2; Room Units 213; 214; 215. Ok to insulate and cover walls. |
| 11/06/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #1; Room Units 103; 104; 105. Ok to insulate and cover walls. |
| 11/04/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #1; Room Units. 101; 102. Ok to insulate and cover walls. |
| 11/02/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 11/02/2020 |
FRAMING |
|
Not ready for Inspection |
CONTRACTOR CANCELED |
| 11/02/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 10/29/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2; Room Units #201; 202; 210; 211; 212; 213; 214; 215; 216; 217 |