Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 07/27/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 11/05/2020 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial. Garage Area; Section D; Level B-1: Air Shafts Southwest; Northwest; Northeast: CMU walls topped out. Section D; Level B-1 Retail Elevator Walls North and East at 8’-12’. Ok to grout progress areas. |
| 11/02/2020 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial. Garage level; Air shafts North 4’-10’; air shaft Northwest- topped out. Level B1; Stairwell C and elevator; top out. Passenger elevator- top out. Ok to place grout in progress areas. |
| 10/20/2020 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial. Parking garage Levels; Passenger elevators #1 & #2 at 0’-4’; Stairwell A/ Elevator E-2 at 4’-8’; North vent shafts #1 & #2 at 4’-8’; storage room Northeast at 4’-8’; Stairwell C at Level B-1 at 4’-8’. Ok to place grout in progress areas. |
| 09/15/2020 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial. Level #1; CMU walls at GL: 9/A-B (0’-4’); 8/A-B (0’-4’); E.3/9-8 (top out); F.2/8-9 (top out); 5/A-E (top out); 6/A-B (top out). Ok to place grout in progress areas. |