Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T19CM02310
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/24/2020 | BUILDING PRE-SLAB | Approved | Approved | |
11/18/2019 | BUILDING PRE-SLAB | Partial Approval | Post Tension Cable System at Level #2; slab #242; GL: A-H/4.8-7. Ok to place concrete in progress areas. | |
11/14/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Inspection to be reschedule for 15 November. | |
11/07/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Contractor cancelled. Rescheduled for 8 November. | |
10/24/2019 | BUILDING PRE-SLAB | Partial Approval | Pre-slabs, laundry, mechanical room, electrical room, fire pump room. Stair 1,2 Pour #2. Ok to place concrete. |
|
10/22/2019 | BUILDING PRE-SLAB | Partial Approval | Partial. Building pre-slab, moisture barrier with #3 rebar reinforcement at GL: B-.5A/10-14. Ok to place concrete. | |
10/21/2019 | BUILDING PRE-SLAB | Partial Approval | 6" slab at GL: M/8-14; 14/M-E; E/8-14; 8/E-M. Ok to place concrete in progress areas. 6" slab with #3 rebar reinforcement at 18" O.C. | |
10/18/2019 | BUILDING PRE-SLAB | Not ready for Inspection | will reschedule for 21 October. | |
10/10/2019 | BUILDING PRE-SLAB | Partial Approval | Inspection should have been 02010: Electric conduit lines at electric room: 36 lines at 3/4"; 6 lines at 2 1/2"; 1 at 2"; 9 at 3"; 1 at 4". Ok to cover progress areas. | |
10/03/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Contractor cancelled. | |
10/01/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Should have called: 02010 and 03005 | |
09/24/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Rained out. | |
09/20/2019 | BUILDING PRE-SLAB | Not ready for Inspection | contractor cancelled. | |
09/17/2019 | BUILDING PRE-SLAB | Not ready for Inspection |