Permit: T19CM02310

Parcel: 11720029A


Addresses:

280 S CHURCH AV

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
06/24/2020 BUILDING PRE-SLAB Approved Approved
11/18/2019 BUILDING PRE-SLAB Partial Approval Post Tension Cable System at Level #2; slab #242; GL: A-H/4.8-7. Ok to place concrete in progress areas.
11/14/2019 BUILDING PRE-SLAB Not ready for Inspection Inspection to be reschedule for 15 November.
11/07/2019 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled. Rescheduled for 8 November.
10/24/2019 BUILDING PRE-SLAB Partial Approval Pre-slabs,

laundry, mechanical room, electrical room, fire pump room.

Stair 1,2

Pour #2.

Ok to place concrete.
10/22/2019 BUILDING PRE-SLAB Partial Approval Partial. Building pre-slab, moisture barrier with #3 rebar reinforcement at GL: B-.5A/10-14. Ok to place concrete.
10/21/2019 BUILDING PRE-SLAB Partial Approval 6" slab at GL: M/8-14; 14/M-E; E/8-14; 8/E-M. Ok to place concrete in progress areas. 6" slab with #3 rebar reinforcement at 18" O.C.
10/18/2019 BUILDING PRE-SLAB Not ready for Inspection will reschedule for 21 October.
10/10/2019 BUILDING PRE-SLAB Partial Approval Inspection should have been 02010: Electric conduit lines at electric room: 36 lines at 3/4"; 6 lines at 2 1/2"; 1 at 2"; 9 at 3"; 1 at 4". Ok to cover progress areas.
10/03/2019 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled.
10/01/2019 BUILDING PRE-SLAB Not ready for Inspection Should have called: 02010 and 03005
09/24/2019 BUILDING PRE-SLAB Not ready for Inspection Rained out.
09/20/2019 BUILDING PRE-SLAB Not ready for Inspection contractor cancelled.
09/17/2019 BUILDING PRE-SLAB Not ready for Inspection