Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T19CM02310

Parcel: 11720029A


Addresses:

280 S CHURCH AV

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
06/24/2020 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
06/24/2020 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
03/02/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Trash enclosure footings as per Civil plan C6.1; structural plan 2.0 details #230; 234; RFI #143. Ok to place concrete in progress area.
02/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval South side screen wall footings at GL: 2.5-5/112. OK to place concrete in progress areas.
02/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #5; Elevator shear wald; need embed at Southwest all junction. Ok to place concrete in progress area.
11/14/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #2; Elevator shear walls; concrete columns at GL: A/6; B/11; D/5; D/6; D/9; D/13; G/5; G/6. Ok to place concrete in Progress areas.
10/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pit area (Hydronic piping). Ok to place concrete in progress area.
GL: L-M/12-14.
10/17/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footing at GL: K/14. Ok to place concrete in progress area.
10/10/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Inspection should have been 01020: stem walls at GL: A.4/2-2.5; 13.9/L-M both walls at 0-4’. Vault walls at K.5-M/7-8. Ok to place concrete in progress areas.
10/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-1 footing at GL: 12/H-L; 14/J-L; F-2 footing at 14/G-F; Ramp wall footings at 13/A-G. East vault mat. Ok to place concrete in progress areas.
09/19/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
09/18/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Concrete columns at GL: 112/7.25; 112/5; 112/4.25; 112/3.75; 112/2.5. Ok to place concrete in progress areas.
09/17/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns at GL: 112/12; 112/11.25; 112/7.25; 112/5.75; 111/11.25; 111/7.25..
09/16/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Concrete columns at GL: G/1; G/5. Stairwell #2; Shear Walls #7 &8. Ok to place concrete in progress areas. Columns and shear walls to pour today: A/4; G/1; C/1; Shear walls #3, 4, 5, 6. Columns, pier caps, continuous footings poured 13 September: Columns: A/9; A/3; C/2; E/4; G/4: Pier caps: G/1; 112/12; 112/11.25; 112/7.5; 112/5.75; A/14. Pier cap footings: 112/7.5; 112/5; 112/4.25; 112/3.25. Continuous footings: G-EE2/5-7.25; EE2/6-7.25.
09/13/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns: A/3, E/3; G/3; D/5; C1; A1. Footings at GL: G-J.25/5-7.5; 7.5-6/J.5-K.5. Exterior wall of elevator, Ok to place concrete.
09/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear walls 1 and 2 @ G m/12-14. Columns G M/10,E/3, C/2,A/2,G/2,E/4. Pier cap footings G 112/2.5, 112/3, 112/3.5, 112/4.5, 112/5,112/7.25. Caps at columns 112/5.75, 112/7.5, 112/11, 112/12. Ok to place concrete
09/11/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns D9, D14, A9. Column A13 not ready.
09/10/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Six columns at GL: D/13; D/6; G/12; B/11; D/5; H/14. K to place concrete.
09/09/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear wall #7 (RFI. #152). 2 each #6 rebar added to west end of shear wall. Footing at GL: 7.5/A-.5A. C1 column at D/12.
09/06/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Setting wall forms for shear walls at Northwest grade beams. Will be ready for inspection 9 September.
09/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Elevator shear walls at GL: 10-11.5/E-G.5. Ok to place concrete in progress areas.
09/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footings at GL: M/10-12; 2/B-G; A/1.11-2.5. Ok to place concrete in progress areas.
09/03/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Northwest stairwell/grade beam at GL: L-M/12-14; Southeast stairwell/grade beam at GL: A.25-B/2-2.25. Ok to place concrete in progress areas.
08/30/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footings at GL: M/10-14; 14/L-M; 14/L; 14.2/L-K.5; 14/K.5; K.5/14-14; 13/K.5-A
08/29/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Over head crane pad; rebar and pedestals in place. Ok to place concrete.
08/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and cages to be placed; #30, #34; #61.
08/27/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Elevator pit/ stairwell mat footing at GL: 10/G-E; E/8-11; H.7-E/10; H.2-F.5/11.2. Caisson cages ; 4 each CC4; 6 each CC5 at GL: J/9; G/12; K/9; M/10; D/14; H/14; A/14; J/12; K/12; K/14. Ok to place concrete in progress areas.
08/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Super structure elevator pit; GL: G-E/10; E/8-11; H.7-E/10; H.2-F.5/11.2. Pit to be reinspected 27 Aug for final inspection before placing concrete.
08/23/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and cages. Cages: CC5 (2); #50 at B-C/2-3; #51 at B-A/2-3. Caisson footings poured: #31 at G/6; #32 at D/6; #42 at C/2; #48 at A.5/2.
08/22/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings to be poured: #54; 55; 58; 59 at crane pad area. Hotel caisson footings to be poured at GL: #22 at J/9; #39 at. A/2; #45 at A/4; #56 at A/5. Ok to place concrete in progress areas.
08/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and cages. Cages: #49 at E/3; #50 at B/2.5; #51 at A.2/2.25; #52 at G/2; #53 at G/1; #56 at A/5; #57 at D/5; #60 at C/1; #61 at A/1. Caisson footings to pour: #18, 19; 46; 49; 50; 51; 53; 54; 58; 59 . Ok to place concrete in progress areas.
08/20/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Crane foundation caisson cages: 54 at K/2.75; #55 at J/2.75; #58 at. J/2.25; #59 at K/2.25. Caisson footings to be poured: #11 at F.5; #25 at G/11.4; #26 at E/11; #4 at G/4; #47 at G/3. Ok to place concrete in progress areas
08/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and cages. Cages: #18 at G/10; #19 at E/10; #22 at J/8; #42 at C/2; #44 at E/ 4; #45 at A/4; #46 at A/3; #47 at G/3; #48 at B/2. Caissons poured: #27; #33; #36; #38.
08/16/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and cages: Cages: #33 at D/9; #34 at A
EE2/Ee109; #35 at 7.5/111; #36 at A/6; #37 at 5.75/112; #38 at G/5; #39 at A/2. Caissons to be poured #11; 12; 21; 28. Ok to place concrete in progress areas.
08/15/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisson footings and caisson cages: #30 at EE2-E108; #29 at 7.5-112; #28 at 11.25-112; #27 at B/11; #26 at E/10.75; #32 at D/6; #31 at D/6. Ok to place cages and concrete in progress areas.
08/14/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 13 each caisson cages at: #3 at K/14; #11 at F/11; #12 at K/12; 1#3 at J/12; #17 at GF/11-12; #18 at GF/10; 19 at GF/10; #20 at M/10; #21 at K/9; #22 at J/8; #23 at A/9; #24 at GF/11-12; #16 at A/13. Ok to place concrete in Progress areas.
08/13/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Cages 1 through 6 set in holes, column rebar into cages also inspected and OK on those numbered
08/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caissons 1, 2, 4 drilled to depth. Cages not installed yet however benchmarks and spacing bars have been installed on those numbered.
08/09/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval cassions 1-16. Several cages need rings secured better, make sure they are secure enough so they won’t shift while hooked up to the crane. #16 and #9 rotation of some of the rings are incorrect.