Permit: T19CM02107

Parcel: 12404100A


Addresses:

900 E 2ND ST


Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T19CM02107

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
11/12/2020 PLUMBING - FINAL Approved 1090
08/12/2020 PLUMBING - FINAL Partial Approval Partial. Level 14; Room Units 1400-1436. Plumbing Ok.
08/11/2020 PLUMBING - FINAL Not ready for Inspection Not ready. Level #14; no water in unit rooms. Will reschedule for 12 August.
08/10/2020 PLUMBING - FINAL Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 11 August.
08/08/2020 PLUMBING - FINAL Not ready for Inspection Not ready. Levels #13-14 not ready.
08/07/2020 PLUMBING - FINAL Partial Approval Partial. Level #10; Room Units 1000-1036. Level #11; Room Units 1100-1136. Level #12; Room Units 1200-1236.
08/06/2020 PLUMBING - FINAL Partial Approval Partial. Level #7; Room Units #700-736. Level #8; Room Units 800-836. Level #9; Room Units 900-936.
08/05/2020 PLUMBING - FINAL Partial Approval Partial. Level #4; Room Units #400-436. Level #5; Room Units #500-536. Level #6; Room Units #600-636.
08/04/2020 PLUMBING - FINAL Partial Approval Partial. Level #2 Room Units #200-255. Level #3; Room Units #300-354.
07/29/2020 PLUMBING - FINAL Not ready for Inspection Not ready. Contractor cancelled; will reschedule for 30 July.
07/28/2020 PLUMBING - FINAL Cancelled Canceled by contractor
07/27/2020 PLUMBING - FINAL Partial Approval REVIEW OF WATER DISINFECTION REPORT COMPLETED (for rooms 1307 and 1410)
07/09/2020 PLUMBING - FINAL Partial Approval REVIEW OF WATER DISINFECTION REPORT COMPLETED (for rooms 240 and 342)