Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Approval
Inspection History: BUILDING - FINAL
Permit Number - T19CM02107
Inspection Description - BUILDING - FINAL
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/12/2020 | BUILDING - FINAL | Partial Approval | INSPECTOR APPROVED BUILDING FINAL. PENDING FIRE AND ENGINEERING. | |
11/12/2020 | BUILDING - FINAL | Approved | 1090 | |
08/15/2020 | BUILDING - FINAL | Partial Approval | Partial. Ok to make application for Temporary Certificate of Occupancy for occupation of staff rooms and related areas. | |
08/07/2020 | BUILDING - FINAL | Partial Approval | Partial. Leasing area: Ok to bring in equipment and to train leasing personnel only. Not to be open to the public. Leasing personnel must remain within the designated leasing office areas. | |
08/04/2020 | BUILDING - FINAL | Partial Approval | Partial. Leasing area and leasing offices: ok to place furniture and related equipment only. No personnel to occupy this area. | |
07/31/2020 | BUILDING - FINAL | Not ready for Inspection | Not ready. Contractor cancelled; will reschedule for Room Units plumbing finals on 3 August. | |
07/30/2020 | BUILDING - FINAL | Partial Approval | Partial. Not ready. Contractor cancelled. | |
07/29/2020 | BUILDING - FINAL | Not ready for Inspection | Not ready. Contractor cancelled. | |
07/28/2020 | BUILDING - FINAL | Cancelled | Canceled by contractor | |
07/16/2020 | BUILDING - FINAL | Not ready for Inspection | Not ready. Contractor cancelled. | |
05/29/2020 | BUILDING - FINAL | Partial Approval | Partial. Room Units at Level 4: 400, 401; 402; 403; 404; 405; 407; 409; 410; 411; 412; 413; 415; 417; 418; 419; 420; 421; 422; 430; 431; 432; 433; 434; 436. Level #5: Room Units: 500; 501; 502; 503; 504; 505; 507; 509; 510; 511; 512; 513; 515; 517; 518; 519; 520; 521; 522; 530; 531; 532; 533; 534; 536. | |
05/27/2020 | BUILDING - FINAL | Partial Approval | Partial. Pre-final room walk through: Level #2: Rooms; 200; 201; ;203; 240; 242; 246; 252; 255. Level #3: 300; 301; 303; 305; 307; 309; 310; 311; 312; 313; 315; 317; 318; 319; 321; 322; 340; 342; 344; 348; 349; 350; 351; 354. All areas except for Electric and Plumbing. |