Permit: T19CM02107

Parcel: 12404100A


Addresses:

900 E 2ND ST

Inspection Status: Partial Approval

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
11/12/2020 BUILDING - FINAL Partial Approval INSPECTOR APPROVED BUILDING FINAL. PENDING FIRE AND ENGINEERING.
11/12/2020 BUILDING - FINAL Approved 1090
08/15/2020 BUILDING - FINAL Partial Approval Partial. Ok to make application for Temporary Certificate of Occupancy for occupation of staff rooms and related areas.
08/07/2020 BUILDING - FINAL Partial Approval Partial. Leasing area: Ok to bring in equipment and to train leasing personnel only. Not to be open to the public. Leasing personnel must remain within the designated leasing office areas.
08/04/2020 BUILDING - FINAL Partial Approval Partial. Leasing area and leasing offices: ok to place furniture and related equipment only. No personnel to occupy this area.
07/31/2020 BUILDING - FINAL Not ready for Inspection Not ready. Contractor cancelled; will reschedule for Room Units plumbing finals on 3 August.
07/30/2020 BUILDING - FINAL Partial Approval Partial. Not ready. Contractor cancelled.
07/29/2020 BUILDING - FINAL Not ready for Inspection Not ready. Contractor cancelled.
07/28/2020 BUILDING - FINAL Cancelled Canceled by contractor
07/16/2020 BUILDING - FINAL Not ready for Inspection Not ready. Contractor cancelled.
05/29/2020 BUILDING - FINAL Partial Approval Partial. Room Units at Level 4: 400, 401; 402; 403; 404; 405; 407; 409; 410; 411; 412; 413; 415; 417; 418; 419; 420; 421; 422; 430; 431; 432; 433; 434; 436. Level #5: Room Units: 500; 501; 502; 503; 504; 505; 507; 509; 510; 511; 512; 513; 515; 517; 518; 519; 520; 521; 522; 530; 531; 532; 533; 534; 536.
05/27/2020 BUILDING - FINAL Partial Approval Partial. Pre-final room walk through: Level #2: Rooms; 200; 201; ;203; 240; 242; 246; 252; 255. Level #3: 300; 301; 303; 305; 307; 309; 310; 311; 312; 313; 315; 317; 318; 319; 321; 322; 340; 342; 344; 348; 349; 350; 351; 354. All areas except for Electric and Plumbing.