Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 10/29/2020 |
PLUMBING - ABOVE CEILING |
|
Approved |
|
| 07/23/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level three complete |
| 07/22/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial approval 2nd floor offices and team rooms |
| 07/02/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial.Level 2 south exterior wall corridor. |
| 06/30/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level 3 corridor 371, ok for drywall |
| 05/15/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Ok to finish hard-lid areas on 2nd level. |
| 03/13/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Level one chiller lines, except for mechanical room. |