Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/29/2020 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 03/12/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Area B 2nd & 3rd floor bathroom and mop sink areas. |
| 12/17/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 12/13/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Building drain from yoga room to main building drain; no test at this time, will test at next inspection. |
| 12/03/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 11/08/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Columns 9-12. |
| 10/10/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
From column line 5 to halfway between column lines 8 and 9. |
| 10/03/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Column line 5 west to bldg footprint ok. |