Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T19CM01353
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/14/2019 | BUILDING - PROGRESS | Approved | ||
11/13/2019 | BUILDING - PROGRESS | Partial Approval | Ok to drywall one side on 3rd floor electrical room and corridors. | |
11/12/2019 | BUILDING - PROGRESS | Not ready for Inspection | Builder wanted 2010 Electric Underground. | |
11/05/2019 | BUILDING - PROGRESS | Not ready for Inspection | Builder wanted 1045 Sheet Rock Nailing, however none of installed drywall was fire rated. | |
11/04/2019 | BUILDING - PROGRESS | Partial Approval | Underground elec north of elevator shaft on exterior, feeding 2 interior elec rooms ok to backfill. | |
11/01/2019 | BUILDING - PROGRESS | Partial Approval | Builder wanted 1035 FRAMING | |
10/31/2019 | BUILDING - PROGRESS | Not ready for Inspection | No work to inspect | |
10/30/2019 | BUILDING - PROGRESS | Partial Approval | Wanted 2010 Electric Underground | |
10/29/2019 | BUILDING - PROGRESS | Partial Approval | Wanted 1020 Reinforced Masonry Pregrout and 3040 Plumbing Yard Water Line Test | |
10/28/2019 | BUILDING - PROGRESS | Not ready for Inspection | Not complete | |
10/24/2019 | BUILDING - PROGRESS | Not ready for Inspection | Work incomplete. | |
10/18/2019 | BUILDING - PROGRESS | Not ready for Inspection | stem wall north west corner, work not complete enough to inspect. | |
10/17/2019 | BUILDING - PROGRESS | Partial Approval | Main feed electrical from west electrical room at main building north side going east to column line 7 OK. | |
10/08/2019 | BUILDING - PROGRESS | Partial Approval |