Permit: T19CM01353

Parcel: 128100570


Addresses:

251 S WILLIAMS BL

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
03/11/2021 FRAMING Approved
03/10/2021 FRAMING Not ready for Inspection Not READY, recall inspection and leave contact information.
08/10/2020 FRAMING Not ready for Inspection Not ready
07/31/2020 FRAMING Partial Approval Partial. Main entry and corridor 143, level one ceiling.
07/29/2020 FRAMING Cancelled Inspection canceled
07/28/2020 FRAMING Partial Approval Partial. Level three lobby and hallway along elevators.
07/09/2020 FRAMING Partial Approval Partial. Second floor north soffit/ceiling; First floor bathroom ceilings.
07/08/2020 FRAMING Cancelled Canceled by contractor
07/07/2020 FRAMING Partial Approval Partial. Second floor elevator area.
07/02/2020 FRAMING Partial Approval Partial. Level 2 south exterior wall corridor & level 3 elevator door area.
06/30/2020 FRAMING Partial Approval Partial. Level 3 corridor 371.
06/24/2020 FRAMING Partial Approval Partial. Overhead in vestibule 131B and front of elevator, 1st floor.
06/22/2020 FRAMING Partial Approval partial approval
Level 3
South wall soffit ok for ceiling hard lid install
Restroom hallway from adjoining hallways ok for ceiling hard lid install
04/02/2020 FRAMING Cancelled inspection cancel by contractor
04/01/2020 FRAMING Partial Approval Level one, elevator shaft three levels.
RVI
03/17/2020 FRAMING Partial Approval South side soffit
03/05/2020 FRAMING Partial Approval Yoga, gym, and bike storage.
03/04/2020 FRAMING Partial Approval Level-2 East Mech Shaft Wall; inspected on previous visit.
02/18/2020 FRAMING Partial Approval NE ext framing for E Stair
02/13/2020 FRAMING Partial Approval Ext framing @ East Stair
02/11/2020 FRAMING Partial Approval Second and third floor interior framing OK except elevator and interior stairwell.
02/06/2020 FRAMING Partial Approval S Ext Soffit, E Mech Chase infill
01/13/2020 FRAMING Partial Approval Exterior walls; South wall and West half of North wall.
11/27/2019 FRAMING Partial Approval West exterior wall levels two and three.
11/21/2019 FRAMING Not ready for Inspection Rained out.
11/01/2019 FRAMING Partial Approval Level two, full height walls West end to column eight.