Date Description Inspector Results Comments
10/29/2020 REINFORCED MASONRY PRE-GROUT Approved
07/27/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial approval ok for grout 1st lift stair site wall
04/08/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Unable to make contact for remote inspection.
03/26/2020 REINFORCED MASONRY PRE-GROUT Cancelled SI completed; will forward report to me.
RVI
03/20/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Generator enclosure, first lift
03/19/2020 REINFORCED MASONRY PRE-GROUT Partial Approval First lift basketball court.
12/20/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top out main building south wall OK.
12/19/2019 REINFORCED MASONRY PRE-GROUT Partial Approval to 11’6" from column 9-14b.
12/12/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top out South side Column lines 1-9.
12/10/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 3rd lift, South Side Columns 1-9.
12/02/2019 REINFORCED MASONRY PRE-GROUT Cancelled on-site by contractor. Looked at North half of HCS.
11/27/2019 REINFORCED MASONRY PRE-GROUT Partial Approval First lift from column 11 to 14b. Second lift from columns 3 to 4.
10/29/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 2nd lift, South side to lintels and top-out of West wall.
10/28/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Northeast stairwell at B-14. From steel beam D-8 to steel beam D-12, 1st lift.
10/16/2019 REINFORCED MASONRY PRE-GROUT Denied top out grunted prior to inspection.east elec. room top out.
10/15/2019 REINFORCED MASONRY PRE-GROUT Partial Approval phase 2 stem wall south side CL 1 to CL 8 ok.
10/11/2019 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Unable to access for inspection.
10/10/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top out West wall.
10/08/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 3rd lift west wall face 1.
Electric room t/o 12’.
Shipping and receiving 3 rd lift. N/East end.
10/04/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Second lift West wall main building OK.
10/02/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top-out maintenance building.
09/30/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top our for East and South walls of maintenance building. 4th lift for West and North walls of maintenance building.
09/27/2019 REINFORCED MASONRY PRE-GROUT Partial Approval First lift East wall and East end of South wall from corner to fourth column.
09/20/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Top out maintenance yard.
09/18/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Bond beam missing at stem on west and south west, special inspector to confirm, document to be provided at next inspection.
09/17/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 3rd lift, Outside walls of maintenance building.
09/16/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 2nd lift; Shipping and Receiving and maintenance yard.
09/12/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 2nd lift for maintenance building and 1st lift for maintenance yard.
09/11/2019 REINFORCED MASONRY PRE-GROUT Partial Approval First lift OK at shipping and main electrical room.
09/06/2019 REINFORCED MASONRY PRE-GROUT Partial Approval 1st lift of Maintenance building only; maintenance yard not inspected.