Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 10/29/2020 |
BUILDING PRE-SLAB |
|
Approved |
|
| 08/11/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial approval for west stairs To fire pump room and west side entrance OK to pour stairs |
| 02/28/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
bench ftng |
| 01/29/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
GYM & Yoga |
| 01/15/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
East stairwell and isolation pads OK. |
| 01/10/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
see previous inspection results. |
| 01/09/2020 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
Work incomplete. |
| 12/18/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
Work not complete |
| 12/17/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
East third of level one. Area C and maintenance/electrical room remain. |
| 12/13/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Remainder of main building level one; Northeast projection remains. |
| 11/19/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Level two. |
| 11/18/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Level three. |
| 11/04/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Gl 4 - 8 ok to pour |
| 10/16/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
lvl 3 CL 4.5 to 8.5 deck ok to pour. |
| 10/15/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
lvl 2 GL 4.5 to 8.5 rebar missing at elevator shaft opening. |
| 10/14/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
Work incomplete. |
| 10/11/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
Unable to access for inspection. |
| 10/08/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
2nd for deck walk, still working on details- 210, 214,235. |