Permit: T19CM01353

Parcel: 128100570


Addresses:

251 S WILLIAMS BL

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
10/29/2020 BUILDING PRE-SLAB Approved
08/11/2020 BUILDING PRE-SLAB Partial Approval Partial approval for west stairs To fire pump room and west side entrance OK to pour stairs
02/28/2020 BUILDING PRE-SLAB Partial Approval bench ftng
01/29/2020 BUILDING PRE-SLAB Partial Approval GYM & Yoga
01/15/2020 BUILDING PRE-SLAB Partial Approval East stairwell and isolation pads OK.
01/10/2020 BUILDING PRE-SLAB Partial Approval see previous inspection results.
01/09/2020 BUILDING PRE-SLAB Not ready for Inspection Work incomplete.
12/18/2019 BUILDING PRE-SLAB Not ready for Inspection Work not complete
12/17/2019 BUILDING PRE-SLAB Partial Approval East third of level one. Area C and maintenance/electrical room remain.
12/13/2019 BUILDING PRE-SLAB Partial Approval Remainder of main building level one; Northeast projection remains.
11/19/2019 BUILDING PRE-SLAB Partial Approval Level two.
11/18/2019 BUILDING PRE-SLAB Partial Approval Level three.
11/04/2019 BUILDING PRE-SLAB Partial Approval Gl 4 - 8 ok to pour
10/16/2019 BUILDING PRE-SLAB Partial Approval lvl 3 CL 4.5 to 8.5 deck ok to pour.
10/15/2019 BUILDING PRE-SLAB Not ready for Inspection lvl 2 GL 4.5 to 8.5 rebar missing at elevator shaft opening.
10/14/2019 BUILDING PRE-SLAB Not ready for Inspection Work incomplete.
10/11/2019 BUILDING PRE-SLAB Not ready for Inspection Unable to access for inspection.
10/08/2019 BUILDING PRE-SLAB Partial Approval 2nd for deck walk, still working on details- 210, 214,235.