Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 08/21/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Thermo down. Final. |
| 07/31/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Temp stripe complete. All traffic lanes now open. |
| 07/30/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Speedy on site prepping for temp striping. |
| 07/17/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Walk through with Supervisor to look at paving. Marked out some problem areas for Lee's to address. May move striping to next week from Thursday 7/19. |
| 06/06/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Called Trafficade to place prewarners on 5th St West of Euclid to reflect closed bike path ahead. |
| 05/22/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Meeting with Trafficade and KE&G to discuss revisions to TCP. Trafficade will resumbit for approval. MH 1 is farter south than originally thought and 5th St Crossing of Euclid will require more substantial restriction |
| 05/14/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
TC Check OK. Mobalizing and beginning to pothole. |
| 05/08/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pre construction meeting with KE&G and Trafficade. Will require mill and overlay of all existing Asphalt (in Moratorium areas) that is cut, trenched , or scarred. Roy with KE&G agreed. Pima County was not present. |