Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
Permit Number - T18FC00045
Inspection Description - FIRE SPKLR - OH PIPING & HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/19/2019 | FIRE SPKLR - OH PIPING & HYDRO | Approved | 10th floor OH @ 207 PSI | |
05/14/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | TESTED THE FIRE PUMP. COMFIRMED SIGNALS TO THE FACP AND OFSITE MONITORING COMPANY | |
05/02/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 9th floor OH Hydro Approved @ 210 PSI | |
05/01/2019 | FIRE SPKLR - OH PIPING & HYDRO | Cancelled | To re-open the permit | |
03/28/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 8th floor OH Hydro @ 205 PSI | |
03/19/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 7th floor OH Hydro 209 psi - approved | |
03/18/2019 | FIRE SPKLR - OH PIPING & HYDRO | Not ready for Inspection | To extend permit | |
03/07/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Partial inspection aproved for residential units on first floor. One unit has HVAC vent too close to sprinkler head. Relocate head or vent. -A Sprinkler head shall be added at the top of each of the passenger elevator shafts. -A re-inspection fee has been added. -Intermediate temp head can be 12 inches to the side of a wall mounted difuser, Ordinary temp heads are 24 inches to the side. |
|
03/05/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 6th floor OH Hydro 207 psi | |
03/01/2019 | FIRE SPKLR - OH PIPING & HYDRO | Denied | no inspection. broken pipe. they did not contact our unit to cancel. OH inspection on CM permit was closed due to contractor not understanding they need to call this permit for sprinkler inspections. all notes to go under this permit. RI fee for todays inspection. | |
02/04/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 4th floor OH/piping and hydro. hydro not needed on unit #407 per C.B. Reinspection fees added. RI fees will be added for each additional inspection. Sprink heads in elevator pits to remain. We are waiting on cut sheets for the elevator belts to determine if sprinkler coverage is needed at the top of the shaft. | |
01/23/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 3rd Floor OH/Piping & Hydro | |
01/09/2019 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 2nd Floor OH/Piping & Hydro | |
08/14/2018 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Fire Inspection 1. Going to be done in phases. Re-inspection fees will incur after 3 inspections. Floors B2 and B1 approved. Level 1 Partial approval, final hydro done when rest of piping is installed on the south units. |