Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 07/18/2019 |
ELECTRIC - UNDERGROUND |
|
Approved |
|
| 03/21/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
solar conduits ok from SES’s to inverters |
| 03/12/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Ok to backfill electrical underground from outside ses to transfer switch to backup generator |
| 12/06/2018 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
West side conduit for parking lot lights. South side conduits for middle row of parking lot lights. |
| 12/04/2018 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Risers at SES on north of building ok, conduits between light poles north lot ok. |
| 11/30/2018 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Conduit at closure pour ok |