Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
3050 S M L KING JR WY
Apply Date:
08/03/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SHELL BLDG
Architects:
  • GARCIA DAVID V
Contractors:
  • RENAISSANCE COMPANIES , THE

Permit Reviews

Permit Number - T18CM06028
Permit Status: Final
Permit Description: SHELL BLDG
Start Date Submittal Complete Date Status  
08/03/2018 PLANS OK TO SUBMIT - COMM 08/03/2018 COMPLETED Review Details
08/03/2018 3RD PARTY REVIEW - COMMERCIAL 09/11/2018 COMPLETED Review Details
09/11/2018 POST 3RD PARTY REVIEW 09/21/2018 COMPLETED Review Details
10/10/2018 REVISION - - 1ST 10/10/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM06028
Permit Status: Final
Permit Description: SHELL BLDG
Total Outstanding Activity Conditions - 1
Date Name
08/03/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T18CM06028
Permit Description: SHELL BLDG
Total Completed Inspections - 38
Date Description Inspector Results Comments
09/20/2018 PLUMBING - FINAL GKOZIOL Approved ISSUED WITH CONDITIONS: NO PHYSICAL CONNECTION TO THE PUBLIC SEWER UNTIL THE PUBLIC SEWER G-2018-069 IS ACCEPTED AND RELEASED BY PCRWRD NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION(D.A.) IS ISSUED FOR G-2018-069 BY PCDSD

NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PUBLIC SEWER G-2018-069 IS ACCEPTED AND RELEASED BY PCRWRD ADDITIONAL CONDITION: THE PUBLIC SEWER G-2018-069 IS NOT APPROVED AS YET BY PCDSD

THE OWNER ASSUMES THE RISK FOR ANY CHANGES TO THE PUBLIC SEWER THAT AFFECT THE GEICO BUILDING CONNECTION SEWER (BCS-PRIVATE SEWER)
10/30/2018 BUILDING PRE-SLAB RCAMACHO Approved After-hours inspection APA account $165 Switchgear pad southeast of substation half of pad only East half 16 foot
10/30/2018 ELECTRIC - TEMPORARY SERVICE RCAMACHO Approved
12/06/2018 ELECTRIC - UNDERGROUND RCHANDLER Approved West side conduit for parking lot lights. South side conduits for middle row of parking lot lights.
12/06/2018 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved Complete building.
12/11/2018 PLUMBING - PRE SLAB DMCCARTHY Approved plumbing pre-slab for water supply and roof drain inside previously poured floor for tilt up new
12/27/2018 ELECTRIC - OUTDOOR LIGHTING RCHANDLER Approved Light poles SW parking lot.
04/10/2019 PLUMBING - MD GAS/PRECONST MTG MHASSAN Approved building has no med gas
07/18/2019 ELECTRIC - CONSTRUCTION POWER MHASSAN Approved
07/18/2019 MECHANICAL - ABOVE CEILING MHASSAN Approved MISSING INSPECTIONS SHOULD BE UNDER TI PERMIT
07/18/2019 MECHANICAL - INTERMEDIATE MHASSAN Approved
07/18/2019 SITE - SEWER MHASSAN Approved
07/18/2019 PLUMBING - SEWER HCS CONNECT MHASSAN Approved
07/18/2019 PLUMBING - ROOF DRAINS MHASSAN Approved MISSING INSPECTIONS SHOULD BE UNDER FOUNDATION OR TI PERMITS
07/18/2019 PLUMBING - ABOVE CEILING MHASSAN Approved
07/18/2019 PLUMBING - INTERMEDIATE MHASSAN Approved MISSING INSPECTIONS SHOULD BE UNDER THE TI
07/18/2019 PLUMBING - ROUGH, SOIL MHASSAN Approved
07/18/2019 ELECTRIC - CABLE DROP MHASSAN Approved
07/18/2019 ELECTRIC - ABOVE CEILING MHASSAN Approved ANY MISSING INSPECTIONS SHOULD BE UNDER THE TI PERMIT
07/18/2019 ELECTRIC - INTERMEDIATE MHASSAN Approved FOR MISSING INSPECTIONS SEE TI AND FOUNDATION PERMITS
07/18/2019 ELECTRIC - UFER MHASSAN Approved
07/18/2019 SHEET ROCK NAILING MHASSAN Approved
07/18/2019 U VALUE FOR WINDOW MHASSAN Approved
07/18/2019 BUILDING ABOVE CEILING MHASSAN Approved THESE INSPECTIONS WERE UNDER TI PERMIT
07/18/2019 STUCCO MESH MHASSAN Approved
07/19/2019 NPPO - FINAL BBENEDON Approved
07/19/2019 SIGN - FINAL BBENEDON Approved
07/19/2019 LANDSCAPE - FINAL BBENEDON Approved
07/19/2019 FIRE SPKLR - FINAL Bravin Approved No issues
07/22/2019 OUTDOOR LIGHTING FINAL MHASSAN Approved
07/22/2019 MECHANICAL - FINAL MHASSAN Approved
07/22/2019 FIREWALL/FIREBARRIER/FIRESTOP MHASSAN Approved
07/22/2019 FRAMING MHASSAN Approved
07/22/2019 EXT METAL CLIPS/EXT SHEATHING MHASSAN Approved
07/22/2019 STEM WALL/RETAINING WALL MHASSAN Approved
10/29/2019 ENGINEERING - FINAL BBENEDON Approved Approved pending approval of the development package permit. I spoke with Jim asked him to schedule all of the remaining items And to provide the latest set of city approved plans
10/18/2022 ELECTRIC - FINAL CTREVIL Approved
10/18/2022 BUILDING - FINAL CTREVIL Approved