Permit: T18CM00946

Parcel: 11504498B


Addresses:

850 E SPEEDWAY BL


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T18CM00946

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
12/03/2019 ENGINEERING - FINAL Approved
11/20/2019 ENGINEERING - FINAL Not ready for Inspection Complete the work for the development package permit. Correct the slope in front of the stair on the ground floor parking in. Currently has 2.3% cross slope. Restrain the accessible parking space. Dave Roberts phone number was provided to the gentleman working
11/14/2019 ENGINEERING - FINAL Not ready for Inspection COMPLETE ALL REPAIRS ON THE ADA PARKING SPACE AND ACCESS AISLE ON THE 1st FLOOR OF THE PARKING STRUCTURE PRIOR TO CALLING IN FOR THE FINAL INSPECTION FOR THIS SITE.
10/29/2019 ENGINEERING - FINAL Partial Approval COMPLETE ALL WORK ON THIS SITE PER THE APPROVED PLANS PRIOR TO REQUESTING ANY ADDITIONAL INSPECTIONS. A RE-FEE WILL BE REQUIRED FOR ALL INCOMPLETE WORK ON THIS SITE.
10/17/2019 ENGINEERING - FINAL Not ready for Inspection COMPLETE ALL WORK AS PREVIOUSLY NOTED ON PAST INSPECTIONS
10/10/2019 ENGINEERING - FINAL Not ready for Inspection Complete the work for the development package permit. I Walked the site with Antonio. Accessible parking space and loading zone and lower level exceeds the maximum allowable slope
08/15/2019 ENGINEERING - FINAL Not ready for Inspection COMPLETE ALL EXTERIOR WORK AND REMOVE ALL EQUIPMENT FROM AROUND THE PEDESTRIAN ACCESS AREA. GENERAL CLEANUP OF THE SITE IS NEEDED PRIOR TO ISSUANCE OF THE TEMPORARY CERTIFICATE OF OCCUPANCY.
08/07/2019 ENGINEERING - FINAL Partial Approval OK FOR A TEMPORARY CERTIFICATE OF OCCUPANCY FOR THIS SITE PENDING ALL OTHER INSPECTIONS.
THIS SITE STILL HAS UNRESOLVED ISSUES CONCERNING THE ADA PARKING AND ACCESS AISLES IN THE PARKING STRUCTURE THAT WILL NEED TO BE RESOLVED PRIOR TO THE FINAL APPROVAL.
07/25/2019 ENGINEERING - FINAL Partial Approval CREWS ARE STILL WORKING ON THE NORTH, EAST, AND WEST SIDES OF THIS SITE ON SITE WORK. THERE IS STILL A DRAINAGE CONCERN IN THE ALLEY ON THE WEST SIDE OF THE BUILDING APPROXIMATELY 50 TO 75 FEET SOUTH OF THE NORTHWEST CORN. THE ROOF DRAINAGE LINES AND THE CURRENT SLOPE GRADES IN THE ALLEY ALLOW THE WATER TO DRAIN BACK TOWARDS THE DOOR OPENINGS. I HAVE BEEN ADVISED BY THE CONTRACTOR THAT THEY HAVE AN RFI INTO THE ENGINEER OF RECORD FOR THIS CONCERN, THEY ARE WAITING FOR HIS RESPONSE. THE PARKING STRUCTURE ON THE FIRST FLOOR STILL HAS MATERIAL BEING STORED IN THE 1ST ADA PARKING SPACES, WE ARE UNABLE TO CHECK THEM AT THIS TIME.
07/24/2019 ENGINEERING - FINAL Partial Approval Engineering has no issues that would prevent a temporary certificate of occupancy
07/19/2019 ENGINEERING - FINAL Partial Approval Engineering has no issues that would prevent a temporary certificate of occupancy
07/10/2019 ENGINEERING - FINAL Not ready for Inspection Work is ongoing and all sides of the project, including site work and building façade, work being performed in the right of way on all sides of the project.
There is dirt, debris, construction material and a dumpster on sidewalks and in the streets. Sidewalks are incomplete around the building. Final grading is being performed in the alley to the west. Sidewalk scuppers have not yet been installed, roof drain terminations have not been completed. Please schedule inspections from the development package permit as work is completed for final inspection.
No message or contact information was provided, I did not find the superintendent on the site.
12/17/2018 ENGINEERING - FINAL Not ready for Inspection Inspection due to a complaint of track out. See inspections on dp1 70301. Antonio at 6:02 795-3440. Is reminded to control and clean and attract out and to schedule inspections under the development package permit.