Date Description Inspector Results Comments
07/16/2019 MECHANICAL - ABOVE CEILING Approved
06/14/2019 MECHANICAL - ABOVE CEILING Partial Approval Computer room.
06/13/2019 MECHANICAL - ABOVE CEILING Partial Approval Yoga room Is ready for sheet rock. Computer room second layer of sheet rock, however missing fire caulk.
06/12/2019 MECHANICAL - ABOVE CEILING Partial Approval MEP’s only for lobby, missing two hour firewall between lobby and fitness Center. The yoga room is not complete
06/05/2019 MECHANICAL - ABOVE CEILING Partial Approval Level #2; Fire dampers. Rooms : 206; 207; 208; 209; 210.
Penetrations in fitness area are Fire caulked,