Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
Permit Number - T18CM00946
Inspection Description - PLUMBING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2019 | PLUMBING - FINAL | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED | |
| 08/15/2019 | PLUMBING - FINAL | Partial Approval | Paint exposed PVC pipes. Pending chlorine report. | |
| 08/07/2019 | PLUMBING - FINAL | Partial Approval | On site with Armando, open issues still not addressed. Still have openings in corridor walls and ceilings. There’s no separation between construction and public. | |
| 08/05/2019 | PLUMBING - FINAL | Not ready for Inspection | Will recall for 7 August. | |
| 08/02/2019 | PLUMBING - FINAL | Partial Approval | For possible TCO occupation. | |
| 07/31/2019 | PLUMBING - FINAL | Partial Approval | Levels 2, 3 and 4 are complete. Lobby, office area and town houses are complete. Missing drain covers under pool, no electric at pool deck, no electric at fitness center and yoga room. Parking garage not ready. |
|
| 07/29/2019 | PLUMBING - FINAL | Partial Approval | Plumbing fixtures not installed, RTU units on roof missing thermostat wires, missing electrical switches and outlets, GFI’s not installed properly. Stopped inspection | |
| 07/25/2019 | PLUMBING - FINAL | Not ready for Inspection | Cancel by contractor | |
| 07/24/2019 | PLUMBING - FINAL | Partial Approval | ADA unit 316 | |
| 07/23/2019 | PLUMBING - FINAL | Not ready for Inspection | Canceled by contractor | |
| 07/22/2019 | PLUMBING - FINAL | Not ready for Inspection | Not complete. | |
| 07/19/2019 | PLUMBING - FINAL | Partial Approval | Units 401 thru 415, 417, 418. All units need to have air handler secured t wall. Unit 416 not ready. |
|
| 07/17/2019 | PLUMBING - FINAL | Partial Approval | Planter and roof drains. | |
| 07/16/2019 | PLUMBING - FINAL | Not ready for Inspection | not complete. | |
| 07/15/2019 | PLUMBING - FINAL | Partial Approval | See note of 01090. | |
| 07/12/2019 | PLUMBING - FINAL | Partial Approval | Level III, units number 301, 302, 303, 304, 305, 306, 307, 309, 310, 315, 317, 318, 314 and 313. Unit number 308. Exhaust fan not working, GFI at kitchen counter is not working. Unit 312, smoke detectors not properly working , disconnect for HVAC does not fully open. Unit number 316 is not ready Unit number 311 and 314, the bathroom GFI‘s are connected to the light and exhaust fan. The kitchen GFI‘s are not properly wired. | |
| 07/11/2019 | PLUMBING - FINAL | Not ready for Inspection | Not complete | |
| 07/10/2019 | PLUMBING - FINAL | Not ready for Inspection | not complete. | |
| 07/05/2019 | PLUMBING - FINAL | Denied | Secured air handler according to manufacturers installation instructions, electrical schedule should match electrical panel, caulk around toilet, remove dryers to inspect dryer vent label and water hammer arrester’s, permanently affixed room number two unit, label disconnects on roof. Stopped inspection. |